NEC4 Contract Preparation · Module 1 of 9

The NEC4 family: which contract for which relationship

After the River Aske floods 140 homes, Aldermere Water approves a GBP 11,200,000 relief scheme. Dana Whitfield, who will be its , then maps who will contract with whom. Learn to pick the NEC4 contract for each line.

21 stepsAbout 19 minutes

Independent course material. It is not published or endorsed by NEC. Short quotes from NEC4 (© NEC 2017) and the FIDIC Red Book (© FIDIC 2017) are used for review and comment. Read the full clauses in your own copy of the contract.

Exhibit 1Dana’s contract map, 29 January 2024
Aldermere Water
The worksECS, or ECSSSubcontracts
Design
Boreholes
Surveys and planting
Maintenance
The Adjudicator
Each line is a contract with Aldermere Water. The subcontracts sit in the Contractor’s box because the Contractor signs them, not Aldermere Water.

Source: Aldermere contract map, 29 January 2024. NEC4 contract title pages.

Key terms

Eight NEC4 contracts you will meet in this module

Terms in this module

Tap a term with a dotted underline anywhere in the lesson to see its meaning.

ECCEngineering and Construction Contract

The NEC4 contract for engineering and construction work with any level of Contractor design. It is the main contract these courses teach.

ECSCEngineering and Construction Short Contract

A shorter NEC4 works contract for simple, low risk jobs. It has no main Options and pays through a Price List.

ECSEngineering and Construction Subcontract

The NEC4 subcontract for works under an NEC4 main contract. The Contractor also takes on the Project Manager's and Supervisor's roles towards the Subcontractor.

ECSSEngineering and Construction Short Subcontract

The short NEC4 works subcontract for simple, low risk work, under an ECC or an ECSC main contract.

PSCProfessional Service Contract

The NEC4 contract for appointing consultants such as designers or project managers. Its main Options are A, C and E.

TSCTerm Service Contract

The NEC4 contract for a service run over a set period, such as maintaining a road network for several years.

DBOCDesign Build and Operate Contract

The NEC4 contract where one contractor designs and builds an asset, then operates it for a service period.

FCFramework Contract

The NEC4 contract that appoints one or more suppliers for a term. Work is then ordered through work orders or time charge orders under other NEC4 contracts.

Source: NEC4 contract title pages and product pages. The course glossary.

The NEC4 family

Most purchases have a main contract, a short contract and a subcontract

Exhibit 2The NEC4 contracts by what is bought
What is boughtMain contractThe Client buysShort contractSimple, low risk workSubcontractWork passed down
WorksBuild, with any level of design, or
Professional servicesDesign and other consulting
Term servicesUpkeep of an asset in use
SupplyGoods, such as pumpsNo NEC4 form
Outside the gridExhibit 8 · · ·

Tap any name for its full title. Module 8 shows how to choose between the ECS and the ECSS.

Source: ECC and ECS title pages. NEC4 product pages.

The NEC4 family

Two Parties sign the ECC, and subcontracts pass work down

Exhibit 3The chain
· a Buys the works
ECC

A , A to F, sets how the Contractor is paid. It brings an , an and .

· Not Parties
Contractor · a Party
, or

The ECS mirrors the ECC, one level down.

  1. Still responsibleThe Contractor stays “responsible for Providing the Works as if it had not subcontracted” (26.1).
  2. Accepted first need the Project Manager’s acceptance (26.2).
  3. DocumentsSent for acceptance, except for an NEC form amended only as the require (26.3).
SubcontractorDoes part of the work

Source: ECC 11.2(13), 26.1, 26.2, 26.3, Schedule of Options. ECS 11.2(11), Schedule of Options.

The NEC4 family

NEC’s test for a short form is risk and complexity, not value

Exhibit 4Five jobs on NEC’s test
Easy to manageHard to manageHigher risk
ECC
GBP 300,000A job on a live railway
ECC
GBP 8,600,000Aldermere’s works: ground, utilities, river
Lower risk
ECSC
GBP 48,000Quarrymoor’s three boreholes
GBP 3,000,000A simple job, design complete
ECC
GBP 240,000Footpaths phased around traffic

Signs of low risk: a finished design, known ground, few likely changes and no alongside.

ECCECSC
Project Manager and SupervisorIn the ECSC the Client manages and may delegateYesNo
Accepted ProgrammeECSC programme needs sit in the ScopeYesNo
Early Warning RegisterYesNo
Main and secondary OptionsA Price List pays in the ECSCYesNo
Quotation sent with the notificationThe ECSC’s shorter procedureNoYes
Client’s liabilities are compensation eventsClause 60.1(14) in the ECCYesNo

The ECSC’s programme requirements sit in its . It pays through a , and the Client carries the quantity risk on rated items. NEC’s July 2023 news adds that the weather compensation event differs.

Source: NEC ECSC product page. NEC comparison note, June 2023. NEC news, July 2023. ECC 60.1(14).

Quick check · The NEC4 family

Two questions on what you have just covered

Quick checkPick an answer to see if you are right and why
1Suppose the winning tenderer plans an ECS for piling, with one extra clause of its own. What must Dana accept before the appointment?
The piling firm only, as the ECS is an NEC form
The piling firm and its subcontract documents
Nothing, as the Contractor stays responsible anyway
2Suppose a Client needs a GBP 150,000 upgrade inside a working treatment plant. Other contractors work alongside, and the design may still change. Which contract fits?
The ECSC, because the value is low
The TSC, because the plant is already in use
The ECC, as the risk and management need are high

2 questions to answer

Source: ECC 26.1, 26.2, 26.3. NEC4 ECSC product page. NEC comparison note, June 2023.

Subcontractors

Three questions decide whether a firm is a Subcontractor

Exhibit 5The 11.2(19) test
  1. 1

    Does it build or install any of the works?

    If yes:
    A A piling firm
    If no, go on to question 2.
  2. 2

    Does it design any of the works? Leave out “the design of Plant and Materials carried out by the supplier” (11.2(19)).

    If yes:
    A SubcontractorA design consultant
    If no, go on to question 3.
  3. 3

    Does it give a service in the needed to ? Leave out hire and people supplied and paid for their working time.

    If yes:
    A SubcontractorSite security
    If no, go on to the outcome.
  4. Not a SubcontractorA maker that only supplies

One yes is enough, for a firm under contract to the Contractor.

Source: ECC 11.2(9), 11.2(14), 11.2(15), 11.2(19), 11.2(20), 26.2.

Subcontractors

Submit each Subcontractor for acceptance before appointing it

Exhibit 6A model submission
What to writeProposed Subcontractor

To: [name], Project Manager

From: the Contractor

Date: [date]

We submit [firm] as a proposed for [the work] (26.2).

Its subcontract is the NEC4 ECS, Option [letter], amended only as the require (26.3).

Amended further? Send the documents, without (26.3). Options C to F: send every subcontract’s pricing information (26.4).

Source: ECC 26.2, 26.3. ECC Options C to F, 26.4.

Services

Services follow the same pattern: a main form, a short form and a subcontract

Exhibit 7Which services contract fits?
Service 1 of 5

…

The PSS and the TSS pass services work down. Module 9 picks the PSC and TSC main Options.

Source: ECC 21.1. NEC4 PSC, PSSC, TSC, TSSC and FMC product pages. NEC news, February 2024.

Other forms

Four forms and one Option join the parties in other ways

Exhibit 8Five other ways to join up the parties
DBOC · one contract
ClientOne contractor
  1. Design
  2. Build
  3. Operate for years

One contractor designs and builds the asset, then runs it.

Its main Options are A and C, each with a price list, and E, cost reimbursable. It runs what it built, so it answers for how the asset performs.

Dana rules it out, as Aldermere Water runs its own network.

ALC · one contract
ClientPartnerPartnerPartnerAlliance Board

The Client and several partners sign one contract.

It has no main Options. One pricing mechanism reimburses cost, with a performance regime on top. An Alliance Board takes decisions and hears disputes first.

Dana rules it out, as one main contractor can deliver the scheme.

X12 · shared objectives and targets
Own Contract
ClientDesigner
Own Contract
ClientContractor

Each firm keeps its own two-party contract, and links them.

“An Own Contract is a contract between two Partners” (X12.1(3)). Payment for meeting a target comes through each Own Contract (X12.4(1)).

The targets sit in the Schedule of Partners, which lists each Partner with its objectives and targets (X12.1(2)). X12 is not used with (Schedule of Options).

FC · a set term
ClientSupplierSupplierSupplier
Work orderECC or ECSCTime charge orderPSSC

One or more suppliers for a set term, to work or supply when instructed.

Each order uses its own NEC4 contract. Work orders usually use the ECC or the ECSC, and time charge orders the PSSC.

Aldermere Water sets one up in 2025 for surveys, minor works and planting.

DRSC · one contract
ClientContractorAdjudicator

Both Parties appoint the under it.

It replaced NEC3’s Adjudicator’s Contract. Under W1 or W2 the Parties use the edition current at the (W1.2(1), W2.2(3)).

A under W3 is appointed the same way (W3.1(2)).

Source: ECC X12.1, X12.2, X12.4(1), W1.2(1), W2.2(3), W3.1(2), Schedule of Options. NEC news, April 2017.

Quick check · Subcontractors and other forms

Two questions on what you have just covered

Quick checkPick an answer to see if you are right and why
1Suppose the winning tenderer hires a design consultant for the Mill Lane pumping station. Must Dana accept the consultant first?
Yes, because it designs part of the works
No, because a designer is only a supplier
No, as it never works in the Working Areas
2Suppose a water company wants its designer and two contractors to work to shared targets. It wants a separate contract with each firm. Which route fits?
The ALC, signed by the Client and all three
The FC, with an order to each firm
X12, laid over each firm’s own contract

2 questions to answer

Source: ECC 11.2(19), 26.2, X12.1, X12.2, X12.4(1).

Your decisions

Three answers set the contracts around your own project

Exhibit 9Decide for your own project

Answer for a project of your own. Each answer shows why it fits, then what Aldermere Water chose.

0 of 3 decided

Which NEC4 contract will you use for the main works?

Judge it by risk and complexity, not by value.

How will you buy design or other professional services?

Think about the size of the commission and how well you can define it.

Who will look after the asset once it is in use?

Think about the years after handover, not just the defects date.

Source: ECC title page, Schedule of Options. NEC4 product pages.

Your strategy

Module 1 fills in the first stage of your contract strategy

Exhibit 10Your contract strategy so far
  1. Module 1 · This moduleThe contract family0 of 3 decided
    1. Works contractNot decided yet
    2. Designer's contractNot decided yet
    3. MaintenanceNot decided yet
  2. Procurement strategyOpens in Module 2
  3. Main OptionOpens in Module 3
  4. Law and disputesOpens in Module 4
  5. Secondary OptionsOpens in Module 5
  6. Contract DataOpens in Module 6
  7. Scope and Site InformationOpens in Module 7
  8. Tenders and subcontractsOpens in Module 8
  9. The other contractsOpens in Module 9
DecidedNot decided yetOpens in a later module

Answers save in this browser. Each module adds a stage.

Source: ECC Schedule of Options.

On the project

Each line on Dana’s January 2024 map becomes a signed contract

Exhibit 11Aldermere Water’s contracts
ClientAldermere Water
PSCApril 2024
DesignHarrowgill Consulting Engineers LLP
ECSCJune 2024
BoreholesQuarrymoor Drilling Ltd
TSCJune 2025
MaintenanceSelbrook Asset Services Ltd
FCOctober 2025
Surveys, plantingThree framework suppliers
December 2025
Tom Barrow
ECCJanuary 2026
WorksThe winning tendererECS, or ECSSSubcontractors
DRSCBoth Parties
DisputesThe
Ruled outAldermere runs its own networkOne main contractor can deliver

Under W1 and W2 alike: “The Parties appoint the Adjudicator under the NEC Dispute Resolution Service Contract” (W1.2(1)), in the edition current at the starting date.

Source: Aldermere contract map, 29 January 2024. ECC W1.2(1), W2.2(3).

On the project

By August 2024 the designer is at work and the borehole logs are in

Exhibit 12January to August 2024
Aldermere Water's first two contracts, January to August 2024Board approval on 15 January and the contract map on 29 January 2024. The PSC on 2 April, the ECSC on 10 June, drilling from 1 to 12 July and the logs on 16 August 2024.JanuaryFebruaryMarchAprilMayJuneJulyAugustAldermereWaterHarrowgillPSCQuarrymoorECSCDrilling1Budget approved2Contract map3PSC signed4ECSC signed5Logs issued
  1. 115 JanBudget approvedAldermere Water The board approves the scheme with a budget of GBP 11,200,000.
  2. 229 JanContract mapAldermere Water Dana Whitfield draws the contract map.
  3. 32 AprPSC signedHarrowgill PSC Aldermere Water signs a PSC with Harrowgill Consulting Engineers LLP for GBP 620,000.
  4. 410 JunECSC signedQuarrymoor ECSC Aldermere Water signs an ECSC with Quarrymoor Drilling Ltd for three boreholes on the culvert line, for GBP 48,000.
  5. 516 AugLogs issuedQuarrymoor ECSC Quarrymoor issues the factual logs of the three boreholes.
115 JanAldermere Water

…

With no Project Manager in the ECSC, Aldermere Water manages Quarrymoor itself. The logs later join the ECC’s .

Source: Aldermere Water, January to August 2024.

Quick check · On the project

Two questions on what you have just covered

Quick checkPick an answer to see if you are right and why
1Suppose Aldermere Water decided to buy the pumps itself and hand them to the works Contractor. Which contract fits that purchase?
The SC, the contract for high value goods
The ECS, as the pumps become part of the works
The PSC, as the maker designs its pumps
2Aldermere’s is 5 January 2026 and its 12 January 2026. Which date fixes the DRSC edition used to appoint the Adjudicator?
The date the first dispute is notified
12 January 2026, the starting date
5 January 2026, the Contract Date

2 questions to answer

Source: NEC4 SC product page. ECC W1.2(1), W2.2(3).

Grey areas

Four questions practitioners ask when they draw the map

Exhibit 13Tap each question for a reasoned answer

The pump maker’s engineer commissions the pumps on . Is the maker now a Subcontractor?

It may be. Commissioning on Site can be a service in the needed to Provide the Works. If in doubt, submit the maker for acceptance.

Clauses 11.2(19), 26.2

The Contractor hires a temporary works designer. Is it a Subcontractor?

Usually not. The design question is about the works, and temporary works are normally : items “the Scope does not require the Contractor to include in the works” (11.2(9)). If its staff give a service on Site, the third question may apply. The Project Manager can still ask for the design to be submitted for acceptance (23.1).

Clauses 11.2(9), 11.2(19), 23.1

A framework supplier plants the embankment beside the works Contractor. Is it a Subcontractor?

No. A Subcontractor is under contract to the Contractor, but this supplier’s contract is with Aldermere Water. Under the ECC it is one of the (11.2(12)). Module 9 shows how the two contracts meet.

Clauses 11.2(12), 11.2(19)

Should the be appointed under a PSC or a PSSC?

The ECC does not say. names the Supervisor, who is not a Party (11.2(13)). One inspector paid for time suits the PSSC. A team with its own procedures suits the PSC. Aldermere Water appoints Tom Barrow under a PSSC on 1 December 2025.

Clause 11.2(13)

Source: ECC 11.2(9), 11.2(12), 11.2(13), 11.2(19), 23.1, 26.2.

Going further

What changed from NEC3, and why term work needs a term form

Exhibit 14For the experienced reader
2017New forms

NEC4 brought the DBOC in 2017 and the ALC in 2018, and the PSC lost NEC3’s Option G, its term contract. Employer became Client, and Works Information became Scope.

X8 to X11X Options filled

NEC4 filled NEC3’s empty to , and added and .

2013Atkins Ltd v Secretary of State for Transport

Lump sum highway upkeep: the amended clause tested each pothole alone, so extra potholes were no compensation event.

DBOCOr two contracts

One DBOC firm answers for years of operation. An ECC then a TSC leaves the handover to the Client.

Source: ECC Schedule of Options. NEC3 ECC Schedule of Options. Atkins Ltd v Secretary of State for Transport (2013).

Watch out

Six mistakes to avoid

Exhibit 15Common mistakes
01Short forms
Defaulting to the ECC for simple work

Test the ECSC first.

NEC ECSC product page
02Value
Choosing a form by contract value

Judge risk and complexity instead.

NEC note, June 2023
03Suppliers
Treating an installer or designer as a supplier

Test it against all three questions.

ECC 11.2(19)
04Amendments
Amending the ECS beyond the Z clauses

Its documents then need acceptance.

ECC 26.3
05Term work
Letting term work on a lump sum

Use a term form, like the TSC.

Atkins (2013)
06Handover
Forgetting what your own staff need

List their manuals, training and spares in the works .

ECC 11.2(2)

Source: ECC 11.2(2), 11.2(16), 11.2(19), 26.3. NEC4 ECSC product page. NEC comparison note, June 2023.

Summary

Every rule in this module, and where to find it

Exhibit 16The rules at a glance
TopicWhat NEC4 says
The ECCA works contract with any level of design, on one main Option from A to F. Its Parties: the Client and the Contractor. Title page, Schedule of Options, 11.2(13)
The ECSA works subcontract below an NEC4 main contract, on Options A to E. Its Parties: the Contractor and the Subcontractor. ECS 11.2(11)
SubcontractingThe Contractor stays responsible. The Project Manager accepts each Subcontractor before it is appointed. Clauses 26.1, 26.2
Subcontract documentsSent for acceptance, without pricing information. Not needed for an NEC contract amended only as the Z clauses require, or if the Project Manager agrees. Under Options C to F, the pricing information of every subcontract goes in as well, unless the Project Manager agrees otherwise. Clauses 26.3, 26.4
Who is a A firm under contract to the Contractor that builds or installs, designs, or gives a needed service in the Working Areas. Left out: a supplier’s design of its Plant and Materials, Equipment hire, and people supplied and paid for their working time. Clause 11.2(19)
Short formsSimple, low risk work that is easy to manage, with no value limit. The ECC treats a Client’s liability as a compensation event, and the ECSC does not. NEC product pages, 60.1(14)
No consultantThe Scope must name any part the Contractor is to design. Clause 21.1
X12Shared targets laid over two-party Own Contracts. Not used with X20. Clauses X12.1, X12.2
The AdjudicatorUnder W1 or W2, both Parties appoint it under the DRSC current at the starting date. Clauses W1.2(1), W2.2(3)

Source: ECC 11.2(13), 11.2(19), 21.1, 26.1, 26.2, 26.3, 60.1(14), W1.2(1), W2.2(3), X12.1, X12.2. ECS 11.2(11).

Check your understanding

Five questions

Quiz
…

Source: see each answer.

Module 1 complete

You can now map the contracts a scheme needs

Your quiz scoreNot taken yet

You can now

  • Name the NEC4 contracts, their short forms and subcontracts, and the relationship each one is for.
  • Use NEC’s test of risk and complexity to choose between the ECC and the ECSC.
  • Test whether a firm is a , and submit it for acceptance.
  • Draw the map of contracts one scheme needs, from design to maintenance.

Independent course material. It is not published or endorsed by NEC. Clause references are to the NEC4 Engineering and Construction Contract, June 2017 with amendments January 2023, unless another NEC4 contract is named. The project and the people are invented. Short quotes from NEC4 (© NEC 2017) and the FIDIC Red Book (© FIDIC 2017) are used for review and comment. Read the full clauses in your own copy of the contract.