WALEED TARIQNEC4 Payment and Defined Cost Masterclass · Module 1: How the ECC pays
Start

NEC4 Payment and Defined Cost Masterclass · Module 1 of 12

How the ECC pays

By 1 June 2026 Merrow Vale Civils has paid GBP 1,905,000 of on Aldermere. Dana Whitfield certifies a payment of GBP 646,020. Follow the money to that figure, then see why Option C is not cost-plus.

20 stepsAbout 19 minutes

Independent course material. It is not published or endorsed by NEC. Short quotes from NEC4 (© NEC 2017) and the FIDIC Red Book (© FIDIC 2017) are used for review and comment. Read the full clauses in your own copy of the contract.

Exhibit 1Aldermere's first five assessments

How the amount due climbed, GBP

9 Feb 2026First assessment date
GBP 234,000
9 Mar 2026
GBP 660,894
6 Apr 2026
GBP 605,106
4 May 2026
GBP 557,730
1 Jun 2026This lesson
GBP 646,020
01,500,0003,000,000
Amount due at the date beforeThe change, which is the payment
Each payment is the change in the : GBP 646,020 on 1 June 2026.

Source: ECC 50.3, 50.5, 51.1, X16.1. ECC Option C 11.2(31). Aldermere Contract Data.

Key terms

Eight terms that carry every ECC payment

Terms in this module

Tap a term with a dotted underline anywhere in the lesson to see its meaning.

Prices

Under Option A or C, the lump sum priced against each activity. Under B or D, the priced bill items. Compensation events change them.

ECC Option C 11.2(32)

Price for Work Done to Date

The basis of each payment. Under Option C it is the Fee plus the Defined Cost the Project Manager expects to be paid out before the next assessment.

ECC Option C 11.2(31)

amount due

The running total owed at an assessment date: the Price for Work Done to Date plus other sums, less deductions. Each payment is the change since the last.

ECC 50.3

Defined Cost

Under Options C to E, the Contractor's costs that the Schedule of Cost Components allows, minus any Disallowed Cost. Options A and B use the Short Schedule instead.

ECC Option C 11.2(24)

Fee

Defined Cost multiplied by the fee percentage. It covers every cost that is not Defined Cost, such as head office overheads, plus profit.

ECC 11.2(10)

Disallowed Cost

Cost the Project Manager removes from Defined Cost, such as cost not backed by records or caused by a missed early warning. It is left out of the amount due.

ECC Option C 11.2(26)

Schedule of Cost Components

The ECC's list of cost types that count as Defined Cost under Options C to E. Each amount counts once and only if spent to Provide the Works.

ECC Schedule of Cost Components

Activity Schedule

The Contractor's priced list of activities under Options A and C. Each activity has a lump sum. Under Option C their total is the target.

ECC Option C 11.2(21)

Source: ECC 11.2(10), 50.3, 52.1. ECC Option C 11.2(21), 11.2(24), 11.2(26), 11.2(31), 11.2(32). Schedule of Cost Components.

The money map

On Aldermere the payment follows cost, and the target waits for the end

Exhibit 2The money map at 1 June 2026
GBP 8,518,385

It is the target. It stays out of the payment until the is assessed at Completion.

  1. GBP 2,775,000

    of GBP 2,500,000, plus of GBP 275,000.

  2. GBP 2,703,750

    A running total, after GBP 71,250 of comes off.

  3. PaymentGBP 646,020

    The change since the 4 May amount due of GBP 2,057,730. Due by 22 June.

“Other payments are the change in the amount due since the previous assessment” (51.1)

Source: ECC 11.2(10), 50.3, 51.1, 51.2, X16.1. ECC Option C 11.2(31), 11.2(32), 54.1, 54.3.

The main Options

The main Option decides what the Price for Work Done to Date measures

Exhibit 3The six main Options

Options A and B pay for work. Options C to F pay cost.

Priced contract with activity schedule

  1. The PricesA lump sum per activity on the , the Contractor's priced list.
    Option A 11.2(32)
  2. Price for Work Done to DateThe Prices of completed activities, and of completed groups of activities.
    Option A 11.2(29)
  3. What Defined Cost doesIt prices with the , a shorter list of cost types.
    Option A 11.2(23)
Paid for work, not cost. The Contractor keeps any saving and carries any overrun.

Priced contract with bill of quantities

  1. The PricesThe : lump sums, and rates times quantities.
    Option B 11.2(33)
  2. Price for Work Done to DateCompleted quantities at the bill rates, plus the completed part of each lump sum.
    Option B 11.2(30)
  3. What Defined Cost doesAs Option A. It prices compensation events with the Short Schedule.
    Option B 11.2(23)
Also paid for work, not cost. Quantities are remeasured, so the Client carries the quantity risk.

Target contract with activity schedule: Aldermere

  1. The PricesActivity lump sums. Their total is the target.
    Option C 11.2(32)
  2. Price for Work Done to Date“the total Defined Cost which the Project Manager forecasts will have been paid” (11.2(31)) before the next . The Fee is added.
    Option C 11.2(31)
  3. What Defined Cost doesIt drives payment: the , less .
    Option C 11.2(24)

With X1, inflation raises the target, not the payment (X1.4).

Target contract with bill of quantities

  1. The PricesAs Option B. The target, the , is remeasured at the bill rates.
    Option D 11.2(33), 11.2(35)
  2. Price for Work Done to DateAs Option C.
    Option D 11.2(31)
  3. What Defined Cost doesAs Option C.
    Option D 11.2(24)
The share compares the Price for Work Done to Date with the remeasured Total of the Prices (Option D 54.5 to 54.8).

Cost reimbursable contract

  1. The PricesA forecast of all the Defined Cost, with the Fee added.
    Option E 11.2(34)
  2. Price for Work Done to DateAs Option C.
    Option E 11.2(31)
  3. What Defined Cost doesAs Option C.
    Option E 11.2(24)
No target and no share. Side case: disallowing GBP 20,000 of hire at an 8% fee costs the Contractor GBP 21,600.

Management contract

  1. The PricesAs Option E: forecast Defined Cost plus the Fee.
    Option F 11.2(34)
  2. Price for Work Done to DateAs Option C.
    Option F 11.2(31)
  3. What Defined Cost doesAmounts due to , plus prices for the Contractor's own work, less Disallowed Cost.
    Option F 11.2(25)
The Contractor subcontracts all but the work the Contract Data says it does itself (Option F 20.2). Paying a Subcontractor for that work, or for management, is Disallowed Cost (Option F 11.2(27)).

Source: ECC Options A to F 11.2(23) to 11.2(35). ECC Option D 54.5 to 54.8. ECC Option F 20.2. ECC X1.4.

The main Options

Under Option A nothing is paid for an activity until it is complete

Exhibit 4Side case outside the Aldermere story
The GBP 180,000 rising main, split as
…
Work done
…
Price paid
…
……………

…

Four equal activities are priced at GBP 45,000 each. Front-loaded puts GBP 90,000 on the first 100 m and GBP 30,000 on each of the rest.

Source: ECC Option A 11.2(29), 11.2(32), 55.4.

The main Options

Options B and D remeasure the bill, and a rate needs its own test

Exhibit 5Side case outside the Aldermere story

The bill has 400 m³ of rock at GBP 45, and 1,100 m³ is dug. Remeasurement pays GBP 49,500.

  1. 1

    Did a change cause the extra rock?

    If yes:
    A under 60.1(1), priced on Defined Cost
    If no, go on to question 2.
  2. 2

    Does the Defined Cost per unit change?

    If no:
    The bill rate stands
    If yes, go on to question 3.
  3. 3

    Is rate × final quantity “more than 0.5% of the total of the Prices at the Contract Date” (60.4)?

    If no:
    The bill rate stands
    If yes, go on to the outcome.
  4. A compensation event: a new rateGBP 49,500 is over 0.5% of the GBP 3,000,000 Prices.

Source: ECC 60.1(1). ECC Option B 11.2(30), 11.2(33), 60.4. ECC Option D 11.2(35), 60.4 to 60.7.

Quick check · The main Options

Two questions on what you have just covered

Quick checkPick an answer to see if you are right and why
1CE007 raised Aldermere's Prices by GBP 81,200 on 5 May 2026. What did that change do to the 1 June payment?
Nothing directly: the work is paid as Defined Cost
It added GBP 81,200 to the Price for Work Done to Date
It added GBP 81,200, plus the Fee on that sum
2On an Option B job, a bill item is 200 m of drain at GBP 120 a metre. The drain is finished at 260 m, with no change to the Scope. What is paid for the item?
GBP 24,000, the billed quantity at the rate
GBP 31,200, the quantity done at the rate
The Defined Cost of the 260 m, plus the Fee

2 questions to answer

Source: ECC 66.2. ECC Option C 11.2(31), 11.2(32). ECC Option B 11.2(30), 60.4.

Defined Cost

Defined Cost is not what you spent: test component, price, then ground

Exhibit 6Test a cost in this order

Costs “not included in the Defined Cost are treated as included in the Fee” (52.1).

  1. 1

    Does a component of the cover it, spent to ?

    If no:
    Never Defined Cost: the Fee covers it
    If yes, go on to question 2.
  2. 2

    Is the price a rate, or an or tendered price?

    If no:
    Only the rate or market price countsThe Fee covers any excess
    If yes, go on to question 3.
  3. 3

    Does a ground of apply?

    If yes:
    Disallowed CostIts Fee goes too
    If no, go on to the outcome.
  4. , with on topNet of discounts, rebates and recoverable tax

Source: ECC 11.2(10), 11.2(15), 52.1. ECC Option C 11.2(24), 11.2(26). Schedule of Cost Components.

Quick check · Defined Cost and payment

Two questions on what you have just covered

Quick checkPick an answer to see if you are right and why
1Merrow Vale pays VAT on a Northway hire invoice and reclaims it. How much of the VAT is Defined Cost?
All of it, because Merrow Vale paid it out
No part of it, as recoverable tax comes off
Half of it, because the share splits it
2Aldermere's Contract Data states no payment period. By when must Aldermere Water pay the sum certified for the 1 June 2026 assessment date?
By 29 June 2026, at the next assessment
By 8 June 2026, one week after it
By 22 June 2026, three weeks after it

2 questions to answer

Source: ECC 51.1, 51.2, 52.1. Aldermere Contract Data.

On the project

Dana counts cost paid by 1 June, plus what she forecasts before 29 June

Exhibit 7Dana's assessment at 1 June 2026
…
…
Defined Cost paid or forecast…
Fee at 11%…
Price for Work Done to Date…
Less retention…
Amount due…
Less the 4 May amount due…
Payment certified…

Retention is 3% of the Price for Work Done to Date above the of GBP 400,000. Move either slider.

Source: ECC 50.3, 51.1, 51.2, X16.1. ECC Option C 11.2(31), 20.4. Aldermere Contract Data.

On the project

A cost that no component covers is a Fee item, not Disallowed Cost

Exhibit 8Sort eight lines from Merrow Vale's ledger

Merrow Vale's regional office is at Kelworth, outside the . Staff based in the Working Areas count in full. Staff based elsewhere count only for their time there, unless the lists them.

Line 1 of 8

…

Modules 5 to 8 cover the components, and Module 10 each ground of Disallowed Cost.

Source: ECC 11.2(20), 52.1. ECC Option C 11.2(26). Schedule of Cost Components, items 11 and 14.

On the project

Option C is not cost-plus: the final bill turns on the target

Exhibit 9The final account, with and without CE007
Suppose

The target ends at GBP 8,912,000. The final Price for Work Done to Date is GBP 8,640,000. Merrow Vale's share is 50% from 90% to 110% of the target, and 25% beyond.

Saving…
…
Merrow Vale's share…
…
Delay damages…
…
0100,000200,000300,000

Delay damages run from the , here 25 May 2027, to on 26 May 2027.

Source: ECC 61.3, X7.1. ECC Option C 54.1, 54.2. Aldermere Contract Data.

What to write

Notify every compensation event: this one was worth GBP 68,600

Exhibit 10The 6 March 2026 notice
What to writeNotification of a compensation event

To: Dana Whitfield, Project Manager, Aldermere Water

From: [your name], Merrow Vale Civils Ltd

Date: 6 March 2026

Compensation event: , clause 60.1(12).

What happened: old concrete foundations in the culvert trench under Station Road.

We became aware of it on 3 March 2026.

In the Toolkit: Letter 02

Send it separately (13.7).

Source: ECC 13.7, 60.1(12), 61.3, X7.1. ECC Option C 54.2.

Quick check · On the project

Two questions on what you have just covered

Quick checkPick an answer to see if you are right and why
1Suppose Dana had forecast GBP 495,000, not GBP 595,000, to be paid before 29 June. What would the 1 June payment have been?
GBP 546,020, exactly GBP 100,000 less
GBP 538,350, with the Fee and retention
GBP 535,020, less GBP 111,000 with the Fee
2On 14 September 2026 Merrow Vale sends Dana its forecast of total Defined Cost for the whole job. What does it do to her 21 September assessment?
It sets the Defined Cost in the assessment
It caps the Price for Work Done to Date
Nothing, as Dana makes her own forecast

2 questions to answer

Source: ECC 11.2(10), X16.1. ECC Option C 11.2(31), 20.4.

Grey areas

Three questions the contract does not fully answer

Exhibit 11Tap each question for a reasoned answer

Each answer says what the clauses settle, then what they leave to practice.

Is the forecast in an Option C payment an advance?

In effect, yes. On 1 June Dana counted GBP 595,000 that Merrow Vale had not yet paid. The 29 June assessment starts again from cost actually paid, so a shortfall makes that payment smaller. Opinion is split on interest. One view treats an over-forecast as a mistake, corrected with interest (51.3). The other says an honest forecast is no mistake. The contract does not decide it.

Option C 11.2(31). Clauses 51.1, 51.3

Can the Project Manager refuse a revised Activity Schedule sent only to help cash flow?

Under Option A, clause 55.3 calls for a revision in two cases only: a changed method of working, or a correction to match the Scope. A re-cut for cash flow is neither. If only the 55.4 reasons may be used, refusing it for another reason is a compensation event (60.1(9)). Most re-cuts fail 55.4 anyway, as loading value onto early activities does not spread the Prices reasonably.

Option A 55.3, 55.4. Clause 60.1(9)

When is an Option A activity with a complete?

When it is “without notified Defects the correction of which will delay following work” (11.2(29)). A cracked chamber cover that holds nothing up leaves it complete. So does a Defect nobody has notified (43.2). The contract does not say whose view of the delay counts. The Project Manager assesses (50.1), so that view prevails in practice.

Option A 11.2(29). Clauses 43.2, 50.1

Source: ECC 43.2, 50.1, 51.1, 51.3, 60.1(9). ECC Option A 11.2(29), 55.3, 55.4. ECC Option C 11.2(31).

Going further

Payment runs on above the target unless a Z clause stops it

Exhibit 12For the experienced reader
Option C 54.1Share after completion

In Doosan Enpure Ltd v Interserve Construction Ltd (2019), the court held the NEC3 share is settled after completion.

Option ZClauses that stop payment

Some Clients add a that caps payment at the target, or holds back part of a forecast overrun. Unamended NEC4 does neither.

11.2(10)One fee percentage

NEC3 had two fee percentages, for subcontracted and direct work. NEC4 has one.

Option A 11.2(29)Fewer Defects hold back payment

NEC3 also counted Defects that later work would cover. NEC4 counts only notified Defects that delay later work.

Source: ECC 11.2(10). ECC Option A 11.2(29). ECC Option C 11.2(31), 54.1. Option Z. Doosan Enpure v Interserve (2019).

Where the rules live

Payment rules sit in five places, and each main Option adds its own

Exhibit 13Where each payment rule lives

The conditions of contract

Core clauses 50 to 53

Every ECC: the amount due, payment, Defined Cost and the final assessment.

Main Option clauses

Your main Option adds its own clauses and picks the cost schedule.

Secondary Options

Only if chosen. Aldermere has X7 delay damages and X16 retention.

The documents

Part one comes from the Client and part two from the Contractor.

How each application looks, extra records and procurement rules.

Payment Options with limits: X1 only with A to D, X3 only with A and B, and X16 never with F.

Source: ECC 50 to 53. ECC Options C to F 20.4, 26.4, 50.9, 52.4. ECC Options C and D 50.7. ECC Options E and F 50.8. ECC Options C, D and E 11.2(26), 52.2. ECC Option F 11.2(27), 52.3. ECC Option C 54.1 to 54.4. ECC Option D 54.5 to 54.8. ECC Option A 55.3, 55.4. ECC Options B and D 60.4 to 60.7. Schedule of Options. Contract Data.

Watch out

Six payment mistakes to avoid

Exhibit 14Common mistakes
01Applications
Treating the application as the payment

The Project Manager assesses the amount due.

ECC 50.1
02Forecasts
Mixing up the two forecasts

Only the Project Manager's forecast sets payment.

Option C 20.4
03Head office
Calling a Fee item Disallowed Cost

It was never Defined Cost.

ECC 52.1
04Late notices
Letting compensation events drift

GBP 1 off Aldermere's target costs GBP 0.50 of share.

ECC 61.3. Option C 54.1
05Option A
Large activities, or front-loading

Big ones pay late, loaded ones early.

Option A 11.2(29)
06Pairings
Banned pairings

Never X16 with F, or X3 with C to F.

Schedule of Options

Source: ECC 50.1, 52.1, 61.3. ECC Option A 11.2(29). ECC Option C 20.4, 54.1. Schedule of Options.

Summary

Every rule in this module, and where the contract keeps it

Exhibit 15The rules at a glance
TopicWhat the contract says
The money mapThe Price for Work Done to Date, plus or minus other sums, is the amount due. Each later payment is the change.Clauses 50.3, 51.1
Options A and BPaid for completed activities or quantities. Defined Cost prices compensation events.Option A 11.2(29), Option B 11.2(30)
Options C to FThe Fee plus Defined Cost forecast to be paid before the next assessment date.Options C to F 11.2(31)
Bill ratesUnder Options B and D the bill is remeasured at its rates. A new rate needs all three tests, and can be lower.Options B and D 60.4
Defined CostA listed component, at a Contract Data rate or a market or tendered price.Option C 11.2(24). Clause 52.1
The FeeOne percentage on Defined Cost. It covers profit and every cost that is not Defined Cost.Clauses 11.2(10), 52.1
Disallowed CostA closed list of grounds. A cost no component covers was never Defined Cost.Option C 11.2(26)
The shareIt turns on the target. A late notice cannot move the Prices, unless the event stems from something the Project Manager or Supervisor did.Option C 54.1. Clause 61.3

Source: ECC 11.2(10), 50.3, 51.1, 52.1, 61.3. ECC Option A 11.2(29). ECC Option B 11.2(30), 60.4. ECC Options C to F 11.2(31). ECC Option C 11.2(24), 11.2(26), 54.1. ECC Option D 60.4.

Check your understanding

Five questions

Quiz
…

Source: see each answer.

Module 1 complete

You can now show why Option C pays cost but is not cost-plus

Your quiz scoreNot taken yet

You can now

  • Trace any ECC payment from the Prices to the amount due.
  • Say how each main Option values work done.
  • Find where each payment rule lives.
  • Sort a cost into Defined Cost, the Fee or Disallowed Cost.

Independent course material. It is not published or endorsed by NEC. Clause references are to the NEC4 Engineering and Construction Contract, June 2017 with amendments January 2023. The project and the people are invented. Short quotes from NEC4 (© NEC 2017) and the FIDIC Red Book (© FIDIC 2017) are used for review and comment. Read the full clauses in your own copy of the contract.

Source: NEC4 Engineering and Construction Contract, June 2017 with amendments January 2023.