WALEED TARIQIs it a valid compensation event? · Module 1: Does the instruction change the Scope?
Start

Is it a valid compensation event? · Module 1 of 4

Does the instruction change the Scope?

On 11 May 2026 the , Dana Whitfield, keeps heavy lorries off Mill Lane at school times. Is that a ?

Compensation event. An event the contract lists as one. It can change the Prices and both kinds of date: the Completion Date and the .

23 stepsAbout 20 minutes

Independent course material. It is not published or endorsed by NEC. Short quotes from NEC4 (© NEC 2017) and the FIDIC Red Book (© FIDIC 2017) are used for review and comment. Read the full clauses in your own copy of the contract.

Exhibit 1Mill Lane on a school day

Minutes barred on each school day

The Scope as it stoodDeliveries to the Mill Lane entrance, 08:15 to 09:00
45 minutes
Dana's 11 May instructionVehicles over 7.5 tonnes, 08:00 to 09:15 and 14:45 to 15:45
135 minutes
050100150
The old windowMorning, from 08:00Afternoon, from 14:45
The new limit is longer and covers every heavy vehicle. It changes a constraint, so it is CE012.

Source: ECC 11.2(16), 60.1, 60.1(1), 66.2.

Key terms

Eight terms you will meet in this module

Terms in this module

Tap a term with a dotted underline anywhere in the lesson to see its meaning.

compensation event

An event the contract lists that can give the Contractor more money or time, such as a Scope change or unexpected ground conditions. Some can reduce the Prices.

ECC 60.1

Scope

Information that describes the works or limits how the Contractor may do them. It sits in documents the Contract Data lists or in an instruction. NEC3 called it Works Information.

ECC 11.2(16)

Contract Data

The project details that complete an ECC. Part one holds the Client's entries and part two the Contractor's. Terms in italics take their values from it.

ECC Contract Data

Provide the Works

The Contractor's core duty: to do all the work needed to finish the works as the contract requires, plus the incidental work and services the contract calls for.

ECC 11.2(15)

Prices

Under Option A or C, the lump sum priced against each activity. Under B or D, the priced bill items. Compensation events change them.

ECC Option C 11.2(32)

Defined Cost

Under Options C to E, the Contractor's costs that the Schedule of Cost Components allows, minus any Disallowed Cost. Options A and B use the Short Schedule instead.

ECC Option C 11.2(24)

Completion Date

The date the Contractor must reach Completion by. It starts as the date written in the Contract Data and moves only under the contract, such as through compensation events.

ECC 11.2(3)

Accepted Programme

The programme the Project Manager last accepted, or the one named in the Contract Data until then. Each accepted programme replaces the one before it.

ECC 11.2(1)

Source: ECC 11.2(1), 11.2(3), 11.2(15), 11.2(16), 60.1. ECC Option C 11.2(24), 11.2(32). Contract Data.

What a compensation event is

Six steps turn a listed event into new Prices and dates

Exhibit 2The route, with CE011's dates

“The following events are compensation events” (60.1)

Clause 60.1 lists 21, and Aldermere's contract adds none.

This course: is it valid?

1The event60.1

16 AprDana's instruction

2Notification61.1, 61.3

8 weeksNot for an instruction

21 AprLeila notifies it

3Reply61.4

Within 1 week

27 AprDana accepts it

Practitioner Course: what is it worth?

4Quotation62.3

3 weeks, then 2 to reply

12 MayGBP 26,085 quoted

5Assessment63.1, 63.5

GBP 23,500 plus the , no delay

6Implementation66.1, 66.2

26 MayThe Prices change

CE011 is Dana's instruction to seal the culvert joints inside, which Module 2 follows. Dana notifies events that come from her own or the 's communications (61.1). Merrow Vale notifies the rest, and any she missed (61.3).

Source: ECC 60.1, 61.1, 61.3, 61.4, 62.3, 63.1, 63.5, 66.1, 66.2.

What a compensation event is

An event that is not valid moves nothing, so validity comes first

Exhibit 3Delay damages at GBP 4,000 a day, with and without the valid events
With no valid events: 26 days late
GBP 104,000
CE007: 7 days, from 5 May 2026
−GBP 28,000
CE014, Dana's assessment: 12 days
−GBP 48,000
CE014, the : 6 more days
−GBP 24,000
Paid: 1 day of
GBP 4,000

For the , changes to the Prices and the dates “are their only rights in respect of a compensation event” (63.6).

Source: ECC 63.6, 66.2, X7.1. ECC Option C 54.1, 54.2.

The full test

Eight questions, in order, decide whether an event is valid

Exhibit 4Take them in order, and stop at the first that ends the matterTaught in this module

Taught in this module

  1. 1Which listed event is it?60.1Modules 1 and 4
  2. 2If it is a communication, did someone with the power give it, with effect?13.1, 13.2, 14.2, 14.3Module 2

An instruction that changes the Scope

  1. 3Does it change the Scope as it stood just before?11.2(16), 60.1(1)Modules 1 and 2
  2. 4Did it settle an , and who provided that Scope?17.1, 63.10Module 3
  3. 5Does an exclusion apply?60.1(1), 45, 46Module 4

Any other event

  1. 6Does every part of its own test hold?60.1(2) to 60.1(21), 60.2, 60.3Module 4, in part

Then, for every event

  1. 7Was it notified in time, and on its own?61.1, 61.3, 61.7, 13.7Modules 2 and 4
  2. 8Does it have an effect, and what does the reply say?61.2, 61.4, W1.1Module 4

Module 4 runs the whole test on two Aldermere events.

Source: ECC 11.2(16), 13.1, 13.2, 13.7, 14.2, 14.3, 17.1, 45, 46, 60.1, 60.2, 60.3, 61.1, 61.2, 61.3, 61.4, 61.7, 63.10, W1.1.

Quick check · The event and the test

Two questions on what you have just covered

Quick checkPick an answer to see if you are right and why
1Merrow Vale's own excavator breaks down for three days. Which question of the full test ends the matter?
Question 1, as no listed event covers it
Question 7, because it was never notified
Question 8, because it has no effect on cost
2Suppose Merrow Vale spends GBP 10,000 of Defined Cost on work that is not a compensation event. With the Fee at 11% and a 50% share, how much does Merrow Vale's share fall?
GBP 5,550
GBP 5,000
Nothing, as it is paid as Defined Cost

2 questions to answer

Source: ECC 11.2(10), 60.1. ECC Option C 11.2(31), 54.1.

What the Scope is

Scope says what to build or limits how, and sits in two places only

Exhibit 5The Aldermere Scope

Place one: the documents the Contract Data lists

Place two: instructions

The
  • The specification
  • The drawings on the drawing list
  • The site constraints

Contract Data part two

The
  • Merrow Vale's design statement for the Mill Lane pumping station

Given under the contract

Each change joins it
  • 24 March 2026: pipe surround, CE009
  • 16 April 2026: culvert joints, CE011
  • 11 May 2026: heavy vehicles, CE012
  • 1 June 2026: embankment slope, CE014

The Scope on any date

It describes the works. It “specifies and describes the works” (11.2(16)).

It sets constraints. It limits how Merrow Vale .

Client's Scope and Contractor's Scope are this course's short names for the two parts (60.1(1)).

Source: ECC 11.2(15), 11.2(16), 60.1(1). Contract Data parts one and two.

What the Scope is

Much of the project paper is not Scope, however much the price relied on it

Exhibit 6Scope or not? Sort seven Aldermere papers
Paper 1 of 7

…

Source: ECC 11.2(16), 11.2(18), 14.1, 20.1. ECC Option C 55.2.

Who can change it

Only the Project Manager, or a delegate she has named, can change the Scope

Exhibit 7The route of a change

Only the “may give an instruction to the Contractor which changes the Scope” (14.3).

What makes the change count

  1. Dana instructsor a named delegate14.2, 14.3
  2. In a lasting formothers can read, copy and keep13.1
  3. Through the portalthe system the Scope names13.2
  4. It changes the Scopea compensation event unless excluded60.1(1)

What follows

Merrow Vale obeys

A duty, not a condition (27.3).

Dana notifies it

When she gives the instruction (61.1).

Or Merrow Vale does

If she does not, with no eight-week bar (61.3).

Source: ECC 11.2(16), 13.1, 13.2, 14.2, 14.3, 27.3, 60.1(1), 61.1, 61.3.

Who can change it

A direction from anyone else changes nothing until Dana instructs it

Exhibit 8Who can change the Aldermere Scope?
WhoCan change the Scope?
Dana WhitfieldThe
Yes, by instruction (14.3)
A Named in a notice from Dana
Yes, for the actions the notice lists
Tom BarrowThe , who checks the quality of the work
No, unless Dana delegates it to him
Aldermere WaterThe
No, even by letter
The Client's designerAldermere Water's consultant
No, even by email
An early warning meetingA decision there that needs a Scope change
Not until Dana instructs it with the revised (15.4)
Work done on anyone else's word is at Merrow Vale's risk. Ask Dana to instruct it first.

Source: ECC 14.2, 14.3, 15.4, 60.1(1), 60.1(4).

Quick check · The Scope and its changes

Two questions on what you have just covered

Quick checkPick an answer to see if you are right and why
1By July 2026 Dana has given several instructions that change the Scope. A new one is tested against which Scope?
The listed documents as they stood at the Contract Date
The listed documents plus every instruction before it
Merrow Vale's Accepted Programme on the day of the instruction
2Dana emails Raj from her phone, outside the portal, to change the working hours. When does her instruction have effect?
When Raj opens and reads the email on site
Once it is sent through the portal
When Raj replies to confirm he has it

2 questions to answer

Source: ECC 11.2(16), 13.2, 14.1.

The test

Compare the instruction with the Scope just before it

Exhibit 9CE012: the Scope beside Dana's instruction

“The Project Manager gives an instruction changing the Scope” (60.1(1))

LineThe Scope just beforeSite constraints, Contract Data part oneDana's instruction11 May 2026, through the portal
VehiclesDeliveriesVehicles over 7.5 tonnes Changed
WhereThe Mill Lane entranceThe whole of Mill Lane Changed
Morning08:15 to 09:0008:00 to 09:15 Changed
AfternoonNo limit14:45 to 15:45 New
DaysSchool daysSchool days

Source: ECC 11.2(16), 14.1, 60.1(1). ECC Option C 55.2.

The test

A compensation event needs the Project Manager's instruction and a real change to the Scope

Exhibit 10Valid compensation event or not?
Case 1 of 6

…

Source: ECC 13.1, 13.2, 14.2, 14.3, 60.1(1), 61.2, 63.4.

Drafting

Most arguments start with the drafting, so make each requirement measurable

Exhibit 11Drafting at Aldermere

Performance

Prescriptive

Client's Scope, performance specification

The wet well passes a flotation check at the highest groundwater level in the .

Contractor's Scope, design statement

A 600 mm wet well base slab.

It sets what the work must achieve. An instruction on method then adds a .

It says exactly what to build, and its writer carries the risk. This slab later failed its check (Module 4).

If the Client's Scope prescribes an answer that cannot meet a performance it also sets, that is an (17.1, Module 3).

  • Vague words such as “as required”Each side reads them its own way.
  • Silence on a detail the work needsNothing on the inside of the culvert joints (CE011).
  • Work to the Project Manager's “satisfaction”No measurable standard.
  • Drawings that do not say who designs what (21.1)No one can tell whose Scope a change touches.
  • One requirement written twice, in different wordsDrawing C-210 and specification 5.12 differed on the outfall pipes (CE009).
  • Requirements in the Site InformationIt describes the Site and is not Scope (11.2(18)).

Source: ECC 11.2(16), 17.1, 21.1.

Quick check · The test and the drafting

Two questions on what you have just covered

Quick checkPick an answer to see if you are right and why
1Suppose Dana instructs a different colour for the kiosk door, and the supplier charges nothing extra. Is the instruction a compensation event?
Yes, but Dana asks for no quotation
No, because nothing costs any more
Only if Merrow Vale can show a delay
2Suppose the Client's Scope prescribes a 450 mm pipe for a drain, and also sets a flow that pipe cannot carry. What is that?
An inconsistency, which either side notifies
A Defect, which Merrow Vale corrects at its cost
A compensation event from the day it is found

2 questions to answer

Source: ECC 17.1, 60.1(1), 61.2, 63.1.

On the project

Leila must decide whether Dana's reply of 5 May changed the Scope

Exhibit 12The Sunday pour, April and May 2026
The Scope as it stood: site constraints

Work 07:30 to 18:00 on weekdays and 08:00 to 13:00 on Saturdays. No work on Sundays.

  1. Tuesday 28 April 2026Raj asks Dana to confirm a Sunday pour of the wet well base on 17 May. Merrow Vale's programme shows it, and its tender price assumed it.
  2. Tuesday 5 May 2026Dana replies that the Scope bars Sunday work.

Is Dana's reply of 5 May a compensation event?

Source: ECC 11.2(16), 14.1, 31.3, 60.1(8). ECC Option C 55.2.

On the project

Dana's school-hours instruction passes the full test, and she notified CE012 the same day

Exhibit 13CE012 run through the full test
Question 1 of 8
QuestionCE012, instructed on 11 May 2026
1Which listed event is it?An instruction changing the Scope, under clause 60.1(1).Listed
2Did someone with the power give it, with effect?Yes. Dana gave it herself, through the portal.Yes
3Does it change the Scope as it stood?Yes. It alters the constraint on vehicles at school times.Changed
4Did it settle an ?No. The Scope was clear, and no two documents conflicted.Clear
5Does an exclusion apply?No. It does not accept a , and it changes the .None
6Does its own test hold?Not needed. Question 6 is for events other than an instruction.Skipped
7Was it notified in time, and on its own?Dana notified it herself on 11 May, so Merrow Vale had nothing to send (61.1).Notified
8Does it have an effect, and what is the reply?Yes. Dana asked for quotations in the same notification (61.2).Valid

Source: ECC 11.2(16), 13.2, 60.1(1), 61.1, 61.2, 62.3, 63.1.

What to write

When the Project Manager is silent, notify the change yourself

Exhibit 14A model notification
What to writeNotification of a compensation event

To: [Project Manager] From: [name]

Date: [date]

We notify a (61.3).

Your instruction of [date] requires [what it asks for].

Just before it, [Scope document and clause] required [what it said].

It changes the Scope provided by the Client and does not accept a Defect (60.1(1)).

The eight-week limit does not apply, as “the event arises from the Project Manager or the Supervisor giving an instruction” (61.3).

Please reply within one week (61.4).

In the Toolkit: Letter 02, Notification of a compensation event

Send it separately, through the portal (13.7).

Source: ECC 13.2, 13.7, 60.1(1), 61.3, 61.4.

Grey areas

Most grey areas turn on what the Scope says, not on what anyone priced

Exhibit 15Questions practitioners ask

The Scope let us choose between two products, and Dana picked one. Is that a change?

Yes. Taking away a choice adds a (11.2(16)). The effect may still be nil. If Merrow Vale would have picked the same product, cost and time do not move (61.2).

More of the same work turned up. Is that a change?

Only where the Scope limits the amount, by a stated quantity or by the extent its drawings show. An instruction to go beyond either is a change (60.1(1)). More work than Merrow Vale measured for the same drawn work is not. Under Option C its cost is shared through the . Extra from the ground is tested under 60.1(12).

The Scope makes the work subject to Dana's satisfaction. Can she ask for more?

The contract has no rule on this wording, and opinion is split. Some say she must judge against what the Scope plainly aims at (10.1, 10.2). Others say Merrow Vale priced the risk. Replace the phrase with a measurable test before tender.

Dana told us how to meet a performance requirement we were missing. Change or not?

Meeting the performance was always required, so that cost stays with Merrow Vale. Fixing the method adds a constraint, so only the extra cost of her method over Merrow Vale's own is assessed (63.1).

An early warning meeting agreed a Scope change. Can we start the work?

Not yet. The agreement is not an instruction. Dana instructs the change when she issues the revised , within a week of the meeting (15.4). Wait for it, or ask for it.

Dana wants to take work out and give it to another firm. Can she?

Taking work out changes the Scope, so it is a compensation event, and a saving can cut the Prices (63.4). No NEC case settles whether she may omit work only to give it to . Ask for her reason in writing and take advice.

Source: ECC 10.1, 10.2, 11.2(16), 14.3, 15.4, 60.1(1), 60.1(12), 61.2, 63.1, 63.4. ECC Option C 54.1.

Going further

Courts read the Scope as written, so a requirement buried in a schedule still binds

Exhibit 16Cases, amendments and NEC3
2017MT Højgaard v E.ON

Not an NEC case. The held that a 20-year design life in a technical schedule bound the contractor, though it met the industry standard the contract named.

2014Wales and West v PPS

The NEC3 lump sum covered coating for 2,000 m of pipe. The contractor said it laid about 8,000 m. An adjudicator found a change worth GBP 479,817.17. The court did not rule on the merits.

Is Atkins (2013) about more of the same work?

No. It turned on a bespoke clause 60.1(11) in a modified NEC3 contract. An arbitrator held that an excess of potholes was not a defect in the road network. The judge said the clause looked at each defect, not the total.

Which amendments narrow clause 60.1(1)?

Clauses saying the Contractor priced anything reasonably inferable, orders of precedence, and query procedures saying answers are not instructions. Read the first.

What changed from NEC3?

became Scope, with the same two-part definition. NEC4 added the communication system rule (13.2). A delegation notice must now name the delegate and the actions (14.2).

Source: ECC 13.2, 14.2, 60.1(1). MT Højgaard v E.ON (2017). Wales and West v PPS (2014). Atkins v Secretary of State for Transport (2013).

Watch out

Five mistakes to avoid

Exhibit 17Common mistakes
01Comparison
Comparing an instruction with your price or programme

Compare it with the Scope just before it.

ECC 11.2(16)
02Authority
Acting on a direction from someone who cannot change the Scope

Only Dana or a notified delegate can.

ECC 14.2, 14.3
03Constraints
Treating a constraint change as a site matter

Constraints are Scope, so changing one is a compensation event.

ECC 60.1(1)
04Tender answers
Leaving tender answers in emails

Fold them into a listed document before the Contract Date.

ECC 11.2(16)
05Order
Arguing about cost before settling whether the Scope changed

The effect is assessed later.

ECC 63.1

Source: ECC 11.2(16), 14.2, 14.3, 60.1(1), 63.1.

Summary

Every rule in this module, and where the contract keeps it

Exhibit 18The rules at a glance
TopicWhat the contract says
A compensation eventAn event the contract lists. Changes to the Prices and dates are the Parties' only rights for it.Clauses 60.1, 63.6
The full testEight questions in order. This module covers questions 1 and 3.Clauses 60.1, 11.2(16)
What Scope isInformation that describes the works or constrains how they are built, in listed documents or instructions.Clause 11.2(16)
Not ScopeThe Site Information, the Activity Schedule, the programme and unlisted tender papers.Clauses 11.2(18), 14.1, Option C 55.2
Who changes itThe Project Manager by instruction, or a delegate named in a notice.Clauses 14.2, 14.3
When it has effectOnce the instruction is in a lasting form and goes through the portal.Clauses 13.1, 13.2
What followsThe Contractor obeys. The Project Manager notifies it, or the Contractor does, with no eight-week bar.Clauses 27.3, 61.1, 61.3
The testCompare it with the Scope just before it, not with the price or the programme.Clauses 11.2(16), 14.1
CostA separate question. A change with no effect gets no instruction to quote.Clauses 61.2, 63.1
Meeting decisionsA Scope change agreed at an early warning meeting counts once the Project Manager instructs it.Clause 15.4

Source: ECC 11.2(16), 11.2(18), 13.1, 13.2, 14.1, 14.2, 14.3, 15.4, 27.3, 60.1, 60.1(1), 61.1, 61.2, 61.3, 63.1, 63.6. ECC Option C 55.2.

Check your understanding

Five questions

Quiz
…

Source: see each answer.

Module 1 complete

You can now test whether an instruction changes the Scope

Your quiz scoreNot taken yet

You can now

  • Say what a is, and where validity sits in the process.
  • Say what is Scope on a contract and what is not.
  • Test an instruction against the Scope as it stood.
  • Spot Scope drafting that invites the argument, and fix it before tender.
  • Tell the Client's Scope from the Contractor's Scope.

The full test so far

  1. 1Which event
  2. 2Power and effect
  3. 3Scope changed
  4. 4Ambiguity or inconsistency
  5. 5Exclusions
  6. 6Its own test
  7. 7Notified in time
  8. 8Effect and reply

Module 2 adds questions 2 and 7. Module 4 runs all eight on two Aldermere events.

Independent course material. It is not published or endorsed by NEC. Clause references are to the NEC4 Engineering and Construction Contract, June 2017 with amendments January 2023. The project and the people are invented. Short quotes from NEC4 (© NEC 2017) and the FIDIC Red Book (© FIDIC 2017) are used for review and comment. Read the full clauses in your own copy of the contract.

Source: NEC4 Engineering and Construction Contract, June 2017 with amendments January 2023.