NEC Case Law, Clause by Clause · Lesson 1 of 4
Where case law comes from
Why it matters
Leila must cite cases on CE014 by 10 August, so which courts count?
A case is only as strong as its court.
- GBP 56,000and 9 days in dispute on CE014, a compensation event.
- 5 Aug 2026Leila Moss, Merrow Vale's commercial manager, checks four cases for its statement of case.
Source: ECC W1.1(2). Module 0.
The rule
An Adjudicator's decision binds its Parties, but only courts make case law
So every case in this course is a court decision.
“binding on the Parties unless and until revised by the tribunal” (W1.3(10))
Adjudicators and arbitrators
Each decision binds only its parties. Most are never published.
Courts
Publish judgments that can bind or persuade later courts.
Source: ECC W1.3(10). Module 0.
The rule
A higher court binds the courts below it in the same system
That is binding precedent. Any other decision can only persuade.
Binds every court below it.
Binds the High Court and, as a rule, itself.
Where most construction cases start.
Source: Module 0.
The rule
Scotland and Northern Ireland have their own ladders
Across systems a decision only persuades. The Privy Council and South Africa sit outside these ladders.
Source: Module 0.
See it on the project
Leila's four cases come from four courts, so name each before she relies on it
Say the court for each case, then tap. None is from Aldermere's own courts.
ICI v Merit Merrell Technology (2018)
NIHE v Healthy Buildings (2017)
UK Grid Solutions (2024)
Sasol v Murray & Roberts (2021)
Source: Module 0. Modules 9, 10 and 13.
Try it
Sort each earlier decision by its weight in the TCC
A TCC judge hears an NEC dispute. Pick a group for each decision she is shown.
…
Binds the judge
- A Court of Appeal decision on the same clause
- A UK Supreme Court decision on English law
Only persuades
- An Inner House decision from Scotland
- An earlier TCC decision by another judge
- A Privy Council decision
Not case law
- An adjudicator's decision between two other firms
Source: Module 0.
Try it
Name the court from each citation, then tap to check
A modern citation gives the year, a court code and a number. Name the court before you tap.
[2013] EWCA Civ 639
[2015] UKSC 36
[2021] CSIH 50
[2026] UKPC 2
Source: Module 0.
Recap
Place each case on its ladder before you rely on it
Three quick checks before any case goes in a notice.
On Monday at work
- Write the court and its level beside each case you cite.
- Check the case comes from your tribunal's legal system.
- Treat an Adjudicator's decision as binding only its Parties (W1.3(10)).
In the Toolkit: NEC4 Contract Checklists (ECC and ECS) (Excel) Members
Independent course material. It is not published or endorsed by NEC, and it is not legal advice. Clause references are to the NEC4 Engineering and Construction Contract, June 2017 with amendments January 2023. Cases decided under an earlier edition are matched to the NEC4 clause that does the same job. The worked examples and their people are invented. Short quotes from NEC4 (© NEC 2017) and the FIDIC Red Book (© FIDIC 2017) are used for review and comment. Read the full clauses in your own copy of the contract.
Source: ECC W1.3(10). Module 0.
Go deeper (optional)
More on the ladders, for later modules
For when you meet these courts later. Skip it if you are short of time.
Who did the Supreme Court's job before October 2009?
What are a proof and a sist in Scotland?
Do courts abroad read similar clauses alike?
What do NICA, NIKB and NIQB mean?
Source: Module 0. Modules 6 and 8.