NEC4 Contract Preparation · Lesson 1 of 3

What makes up an ECC

7 screensAbout 5 minutes

Why it matters

On 5 January 2026 a GBP 8,400,000 contract begins, so which papers form it?

New to NEC4? Start here.

5 Jan 2026the : a culvert, a pumping station and an embankment
GBP 8,400,000the priced from them
A tender letter promises extra testing. Does it bind?

Source: ECC 12.4, Contract Data part one.

The rule

An ECC is a set of documents in four layers

Four layers. Tap each one.

: Engineering and Construction Contract.

  1. The , sections 1 to 9, the same in every ECC.
  2. OptionsOne , one and any .
  1. Options C, D and EThe .
  2. Options A and BThe Short Schedule.
  1. Part oneWritten by the .
  2. Part twoWritten by the Contractor.
  1. What to build, and any limits on how.
    Clause 11.2(16)
  2. What the and its surroundings are like.
    Clause 11.2(18)

Outside it: tender letters, meeting notes and strategy papers.

Source: ECC 11.2(16), 11.2(18).

The rule

Three rules hold it together

No document outranks another.

  1. No rankingEither side notifies a clash. The states how it is resolved.
    Clause 17.1
  2. One agreement“The contract is the entire agreement between the Parties” (12.4).
    Clause 12.4
  3. Signed changesA change not provided for needs both to agree in writing and sign.
    Clause 12.3

Source: ECC 12.3, 12.4, 17.1.

See it on the project

Only listed papers make Aldermere's contract

Decide, then tap to see the answer.

In the contract

part one, written by Dana Whitfield, Project Manager.

Scope: specification and drawings.

Site Information: borehole logs.

Not in it

The strategy paper.

Should Dana also list the designer's ground report as Site Information?

No. She lists only the borehole logs. Anything listed joins the contract, so she keeps the designer's opinions out (11.2(18)). Module 7 shows why.

ECC 11.2(18)

Source: ECC 11.2(16), 11.2(18), 12.4.

Try it

Sort each paper: part of the contract or not

Every answer gives its reason, so a wrong guess still teaches.

Hint: ask whether the Contract Data lists it.

Paper 1 of 6

…

Source: ECC 11.2(16), 11.2(18), 12.4.

Quick check · The three rules

Two questions on what you have just covered

Pick an answer to see why.

Quick checkPick an answer to see if you are right and why
1In March 2026 Dana and the Contractor agree a lower fee percentage by phone. Is the contract changed?
No, it needs a signed change
Yes, a phone call is enough
Yes, once Dana notes it down
2Two Scope documents describe the same headwall differently. Who decides which applies?
The Project Manager
The later document wins
The Client's lawyer

2 questions to answer

Source: ECC 12.3, 17.1.

Recap

Know which documents make the contract before you rely on one

Habits for any NEC4 contract.

On Monday at work

  • Read the first entry of part one to see which conditions apply.
  • Check every document you rely on is listed in the Contract Data (12.4).
  • Notify a clash between documents as soon as you see it (17.1).

In the Toolkit: NEC4 Contract Checklists (ECC and ECS) (Excel) Members

Next lesson: Italics and capitals

Your place is kept in this browser. Create a free account to keep it on every device.

Independent course material. It is not published or endorsed by NEC. Clause references are to the NEC4 Engineering and Construction Contract, June 2017 with amendments January 2023, unless another NEC4 contract is named. The project and the people are invented. Short quotes from NEC4 (© NEC 2017) and the FIDIC Red Book (© FIDIC 2017) are used for review and comment. Read the full clauses in your own copy of the contract.

Source: ECC 11.2(16), 11.2(18), 12.3, 12.4, 17.1.

Go deeper (optional)

Three harder points about the documents

Open them when you have a minute.

A tender letter promises something the listed documents do not. Does it bind?

Not as part of the ECC (12.4). The general law can still decide what formed the contract, so put what you rely on in a listed document (Module 8).

ECC 12.4

Part one names an older printing, such as the October 2020 amendments. Which wording applies?

The one part one names. The January 2023 amendments changed clauses such as 22.1 and W2.3, and added X29.

Contract Data part one

Which letters go where?

Main Options A to F. Dispute resolution Options W1, W2 and W3. Secondary Options X, Y(UK) and Z. Core clauses are numbered 1 to 9.

Schedule of Options

Source: ECC 12.4, Contract Data part one.

Go deeper (optional)

Write a one-page summary the day you first read a contract

Fill it in once.

What to writeContract summary

Contract summary: [contract name]. Read by [name] on [date].

Options: main Option [A to F]. Dispute resolution Option [W1, W2 or W3]. Secondary Options [list].

People: Client [name]. Contractor [name]. Project Manager [name]. Supervisor [name]. Adjudicator [name].

Documents: Scope in [list]. Site Information in [list].

Dates: starting date [date]. Key Dates [list]. Completion date [date].

Money: fee percentage [percentage]. Delay damages [amount] a day.

To notify under clause 17.1: [each unclear or clashing entry, and where it is].

In the Toolkit: checklists

Source: ECC 11.2(16), 11.2(18), 17.1.