NEC4 Contract Preparation · Lesson 1 of 3
What makes up an ECC
Why it matters
On 5 January 2026 a GBP 8,400,000 contract begins, so which papers form it?
New to NEC4? Start here.
Source: ECC 12.4, Contract Data part one.
The rule
An ECC is a set of documents in four layers
Four layers. Tap each one.
ECC: Engineering and Construction Contract.
- Conditions of contractThe core clauses, sections 1 to 9, the same in every ECC.
- OptionsOne main Option, one dispute resolution Option and any secondary Options.
- Options C, D and EThe Schedule of Cost Components.
- Options A and BThe Short Schedule.
- Part oneWritten by the Client.
- Part twoWritten by the Contractor.
- ScopeWhat to build, and any limits on how.Clause 11.2(16)
- Site InformationWhat the Site and its surroundings are like.Clause 11.2(18)
Outside it: tender letters, meeting notes and strategy papers.
Source: ECC 11.2(16), 11.2(18).
The rule
Three rules hold it together
No document outranks another.
- No rankingEither side notifies a clash. The Project Manager states how it is resolved.Clause 17.1
- One agreement“The contract is the entire agreement between the Parties” (12.4).Clause 12.4
- Signed changesA change not provided for needs both Parties to agree in writing and sign.Clause 12.3
Source: ECC 12.3, 12.4, 17.1.
See it on the project
Only listed papers make Aldermere's contract
Decide, then tap to see the answer.
In the contract
Contract Data part one, written by Dana Whitfield, Project Manager.
Scope: specification and drawings.
Site Information: borehole logs.
Not in it
The strategy paper.
Should Dana also list the designer's ground report as Site Information?
ECC 11.2(18)
Source: ECC 11.2(16), 11.2(18), 12.4.
Try it
Sort each paper: part of the contract or not
Every answer gives its reason, so a wrong guess still teaches.
Hint: ask whether the Contract Data lists it.
…
Part of the contract
- The borehole logs for BH1 to BH3
- Contract Data part two, as the winning tenderer completes it
- The specification named in part one as Scope
Not part of it
- The notes of the market day held on 4 June 2025
- A tender letter that promises extra testing
- The strategy paper of 12 February 2025
Source: ECC 11.2(16), 11.2(18), 12.4.
Quick check · The three rules
Two questions on what you have just covered
Pick an answer to see why.
2 questions to answer
Source: ECC 12.3, 17.1.
Recap
Know which documents make the contract before you rely on one
Habits for any NEC4 contract.
On Monday at work
- Read the first entry of part one to see which conditions apply.
- Check every document you rely on is listed in the Contract Data (12.4).
- Notify a clash between documents as soon as you see it (17.1).
In the Toolkit: NEC4 Contract Checklists (ECC and ECS) (Excel) Members
Independent course material. It is not published or endorsed by NEC. Clause references are to the NEC4 Engineering and Construction Contract, June 2017 with amendments January 2023, unless another NEC4 contract is named. The project and the people are invented. Short quotes from NEC4 (© NEC 2017) and the FIDIC Red Book (© FIDIC 2017) are used for review and comment. Read the full clauses in your own copy of the contract.
Source: ECC 11.2(16), 11.2(18), 12.3, 12.4, 17.1.
Go deeper (optional)
Three harder points about the documents
Open them when you have a minute.
A tender letter promises something the listed documents do not. Does it bind?
ECC 12.4
Part one names an older printing, such as the October 2020 amendments. Which wording applies?
Contract Data part one
Which letters go where?
Schedule of Options
Source: ECC 12.4, Contract Data part one.
Go deeper (optional)
Write a one-page summary the day you first read a contract
Fill it in once.
Contract summary: [contract name]. Read by [name] on [date].
Options: main Option [A to F]. Dispute resolution Option [W1, W2 or W3]. Secondary Options [list].
People: Client [name]. Contractor [name]. Project Manager [name]. Supervisor [name]. Adjudicator [name].
Documents: Scope in [list]. Site Information in [list].
Dates: starting date [date]. Key Dates [list]. Completion date [date].
Money: fee percentage [percentage]. Delay damages [amount] a day.
To notify under clause 17.1: [each unclear or clashing entry, and where it is].
In the Toolkit: checklists
Source: ECC 11.2(16), 11.2(18), 17.1.