NEC4 ECC Practitioner Course · Module 1 · Lesson 1 of 4
What makes up the contract
Why it matters
Leila opens the Aldermere contract, so which documents must Merrow Vale follow?
Leila Moss is commercial manager for Merrow Vale, the Contractor. GBP 8,400,000 of work rests on these documents.
Source: ECC 11.2(4). Aldermere Contract Data part one.
The rule
Contract Data names the clauses
Core first, then the chosen Options.
Nine sections, 1 to 9. The first digit of a clause number gives its section.
How the Contractor is paid.
How disputes end.
Extra terms.
Source: ECC Contract Data part one. Options A to F, W1 to W3, X and Y, Z.
The rule
Scope and Site Information sit only in listed documents
Not listed? Not in the deal.
Scope
It “specifies and describes the works” (11.2(16)), and sits in a listed document or an instruction.
Site Information
Describes the Site and its surroundings (11.2(18)).
Merrow Vale is taken to have allowed for it (60.2).
Source: ECC 11.2(16), 11.2(18), 60.2.
The rule
Notify a document clash at once
A Scope change is usually a compensation event.
Priced on the reading “most favourable to the Party which did not provide the Scope” (63.10).
- Spot a clasheither side17.1
- Notify the otherat once17.1
- The Project Manager resolves itby reply17.1
- A compensation eventif Scope changes60.1(1)
Source: ECC 17.1, 60.1(1), 63.10.
See it on the project
Aldermere's Contract Data names Option C, W1, X7 and X16
Decide first.
- Fee percentage
- 11%
Can Leila read Option C clause 50.9 on its own?
Part one names no Option Z. So what?
Source: ECC Option C 50.9. Aldermere Contract Data parts one and two.
Try it
Sort each document Leila finds on the file
Ask one thing each time. Does the Contract Data list it, or does an instruction hold it?
…
Scope
- The culvert specification, which the Contract Data lists as Scope.
- Dana Whitfield, the Project Manager, instructs a flatter embankment slope on 1 June 2026.
Site Information
- The three borehole logs, listed as Site Information.
Neither
- Merrow Vale's tender method statement, which the Contract Data does not list.
- Suppose Aldermere Water emails a new ground survey in March. Nothing lists it.
Source: ECC 11.2(16), 11.2(18), 14.3, 60.2.
Quick check · Clashes
Two questions on what you have just covered
Answer, then read why.
2 questions to answer
Source: ECC 17.1, 60.1(1), 63.10.
Recap
Check the listed documents first, and notify any clash you find
Letter 07 of the ECC Notice Letters is the clause 17.1 notice.
On Monday at work
- Note which Options Contract Data part one names.
- Price and build only from listed Scope.
- Notify each clash at once, in its own notice.
In the Toolkit: NEC4 ECC Notice Letters (zip) Members
Independent course material. It is not published or endorsed by NEC. Clause references are to the NEC4 Engineering and Construction Contract, June 2017 with amendments January 2023. The project and the people are invented. Short quotes from NEC4 (© NEC 2017) and the FIDIC Red Book (© FIDIC 2017) are used for review and comment. Read the full clauses in your own copy of the contract.
Source: ECC 11.2(16), 17.1.
Go deeper (optional)
A clause 17.1 notice names both documents
Send it on its own (13.7).
To: Dana Whitfield
We notify an ambiguity or inconsistency under clause 17.1.
Drawing [number] shows [what]. Specification [clause] requires [what].
Found on [date]. Please state how to resolve it.
In the Toolkit: Letter 07
Source: ECC 13.7, 17.1.
Go deeper (optional)
The main Option sets who carries the cost risk
Optional. The six main Options.
| How the Contractor is paid | Cost risk | |
|---|---|---|
| Option APriced, activity schedule | The Prices of completed activities | Contractor |
| Option BPriced, bill of quantities | Bill rates for the quantities done | Contractor |
| Option CTarget, activity schedule | Defined Cost plus the Fee, with a share | Shared |
| Option DTarget, bill of quantities | Defined Cost plus the Fee, with a share | Shared |
| Option ECost reimbursable | Defined Cost plus the Fee | Client |
| Option FManagement contract | Defined Cost plus the Fee | Client |
Defined Cost is the Contractor's cost under the contract's rules. The Fee is its percentage on top. The Prices come from the activity schedule or the bill. Some secondary Options fit only certain main Options. X16 retention is not used with Option F.
Source: ECC Options A to F. Option X16.
Go deeper (optional)
The 1996 Act decides whether W2 applies
Optional. Why Aldermere uses W1, and what changes on a UK job.
| Adjudication | Dispute Avoidance Board | |
|---|---|---|
| The Act appliesconstruction work in the United Kingdom | W2 | No |
| The Act does not applysuch as Aldermere | W1 | W3 |
The 1996 Act is the Housing Grants, Construction and Regeneration Act 1996. Aldermere is outside the United Kingdom, and Aldermere Water chose adjudication, so the contract uses W1.
Source: ECC Options W1, W2 and W3. Aldermere storyline.
Go deeper (optional)
Two less common cases with the documents
Optional. Two cases worth knowing before they happen on your job.
The Scope asks for something illegal or impossible. What happens?
ECC 17.2
Merrow Vale wrote part of the Scope for its own design. Who gets the favourable reading of a clash in that part?
ECC 63.10
Source: ECC 17.2, 63.10.