Start

NEC4 ECC Practitioner Course · Module 1 · Lesson 1 of 4

What makes up the contract

8 screensAbout 5 minutes

Why it matters

Leila opens the Aldermere contract, so which documents must Merrow Vale follow?

Leila Moss is commercial manager for Merrow Vale, the Contractor. GBP 8,400,000 of work rests on these documents.

5 Jan 2026the , the day the contract was made
The is the index to the whole contract.

Source: ECC 11.2(4). Aldermere Contract Data part one.

The rule

Contract Data names the clauses

Core first, then the chosen Options.

Nine sections, 1 to 9. The first digit of a clause number gives its section.

A A to F

How the is paid.

A W1, W2 or W3

How disputes end.

X, Y and Z

Extra terms.

Source: ECC Contract Data part one. Options A to F, W1 to W3, X and Y, Z.

The rule

Scope and Site Information sit only in listed documents

Not listed? Not in the deal.

Scope

It “specifies and describes the works” (11.2(16)), and sits in a listed document or an instruction.

Site Information

Describes the and its surroundings (11.2(18)).

Merrow Vale is taken to have allowed for it (60.2).

Source: ECC 11.2(16), 11.2(18), 60.2.

The rule

Notify a document clash at once

A change is usually a .

Priced on the reading “most favourable to the Party which did not provide the Scope” (63.10).

  1. Spot a clasheither side17.1
  2. Notify the otherat once17.1
  3. The Project Manager resolves itby reply17.1
  4. A compensation eventif Scope changes60.1(1)

Source: ECC 17.1, 60.1(1), 63.10.

See it on the project

Aldermere's Contract Data names Option C, W1, X7 and X16

Decide first.

Part oneClient: Aldermere Water
Conditions
Core clauses, , , and .
Part twoContractor: Merrow Vale
Fee percentage
11%

Can Leila read Option C clause 50.9 on its own?

No. Each Option C clause is read with the core clause it joins, such as 50.9 with clause 50.

Part one names no . So what?

There are no additional conditions of contract. The core clauses and the chosen Options make up the conditions.

Source: ECC Option C 50.9. Aldermere Contract Data parts one and two.

Try it

Sort each document Leila finds on the file

Ask one thing each time. Does the Contract Data list it, or does an instruction hold it?

Document 1 of 5

…

Source: ECC 11.2(16), 11.2(18), 14.3, 60.2.

Quick check · Clashes

Two questions on what you have just covered

Answer, then read why.

Quick checkPick an answer to see if you are right and why
1Suppose the drawing says 900 mm and the specification 1,050 mm. Which wins?
Neither, until Dana states how to resolve it
The specification, as words outrank drawings
The drawing, as it was issued later
Whichever one Merrow Vale priced
2Aldermere Water wrote the Scope. How is Dana's change priced?
On the reading that favours Merrow Vale
On the reading that favours Aldermere Water
On the cheaper of the two readings
It is not priced, as clashes are at Merrow Vale's risk

2 questions to answer

Source: ECC 17.1, 60.1(1), 63.10.

Recap

Check the listed documents first, and notify any clash you find

Letter 07 of the ECC Notice Letters is the clause 17.1 notice.

On Monday at work

  • Note which Options Contract Data part one names.
  • Price and build only from listed Scope.
  • Notify each clash at once, in its own notice.

In the Toolkit: NEC4 ECC Notice Letters (zip) Members

Next lesson: Who is who

Your place is kept in this browser. Create a free account to keep it on every device.

Independent course material. It is not published or endorsed by NEC. Clause references are to the NEC4 Engineering and Construction Contract, June 2017 with amendments January 2023. The project and the people are invented. Short quotes from NEC4 (© NEC 2017) and the FIDIC Red Book (© FIDIC 2017) are used for review and comment. Read the full clauses in your own copy of the contract.

Source: ECC 11.2(16), 17.1.

Go deeper (optional)

A clause 17.1 notice names both documents

Send it on its own (13.7).

What to writeNotification of an ambiguity or inconsistency

To: Dana Whitfield

We notify an under clause 17.1.

Drawing [number] shows [what]. Specification [clause] requires [what].

Found on [date]. Please state how to resolve it.

In the Toolkit: Letter 07

Source: ECC 13.7, 17.1.

Go deeper (optional)

The main Option sets who carries the cost risk

Optional. The six main Options.

How the Contractor is paidCost risk
Option APriced, activity scheduleThe Prices of completed activitiesContractor
Option BPriced, bill of quantitiesBill rates for the quantities doneContractor
Option CTarget, activity scheduleDefined Cost plus the Fee, with a shareShared
Option DTarget, bill of quantitiesDefined Cost plus the Fee, with a shareShared
Option ECost reimbursableDefined Cost plus the Fee
Option FManagement contractDefined Cost plus the FeeClient

is the Contractor's cost under the contract's rules. The is its percentage on top. The come from the activity schedule or the bill. Some secondary Options fit only certain main Options. X16 retention is not used with Option F.

Source: ECC Options A to F. Option X16.

Go deeper (optional)

The 1996 Act decides whether W2 applies

Optional. Why Aldermere uses W1, and what changes on a UK job.

AdjudicationDispute Avoidance Board
The Act appliesconstruction work in the United KingdomW2No
The Act does not applysuch as AldermereW1W3

The 1996 Act is the . Aldermere is outside the United Kingdom, and Aldermere Water chose adjudication, so the contract uses W1.

Source: ECC Options W1, W2 and W3. Aldermere storyline.

Go deeper (optional)

Two less common cases with the documents

Optional. Two cases worth knowing before they happen on your job.

The Scope asks for something illegal or impossible. What happens?

Whoever spots it tells the other at once. Dana then instructs a change to the Scope (17.2).

ECC 17.2

Merrow Vale wrote part of the Scope for its own design. Who gets the favourable reading of a clash in that part?

Aldermere Water. The reading that suits the that did not write that Scope is used (63.10).

ECC 63.10

Source: ECC 17.2, 63.10.