NEC4 Payment and Defined Cost Masterclass · Lesson 1 of 3
The words that move money
Why it matters
One capital letter changes an NEC4 word's meaning
Each carries a rule.
total of the Prices
Option C: the target for the Contractor's share.
Total of the Prices
Option D only: the Bill of Quantities, as measured.
Source: ECC Option C 54.1. ECC Option D 11.2(35).
The rule
Capitals mark a defined term, italics an identified term
The first letter tells you where to look.
Capitals. Clause 11.2 defines it.
Printed in italics in the contract. The Contract Data sets its value.
A clause says how it works.
“defined terms have capital initials” (11.1)
Source: ECC 11.1, 11.2(10), 50.1, 50.3.
The rule
A defined term can change with the Option
Read your own Option's definition.
Option A
Price for Work Done to Date: the Prices of completed activities.
Option C on Aldermere
Defined Cost the Project Manager forecasts as paid before the next assessment date, with the Fee added.
This course writes C 11.2(31) for an Option C clause.
Source: ECC Option A 11.2(29). ECC Option C 11.2(31).
The rule
Equipment is used, Plant and Materials are built in
Will it stay in the works?
Used for the work, then taken away.
Built into the works.
Builds or designs part of the works, or gives a needed service in the Working Areas. Not Equipment hire or people paid by the hour.
Source: ECC 11.2(9), 11.2(14), 11.2(19).
See it on the project
Aldermere's Contract Data answers four questions
Answer each, then open it.
Completion comes a day late. What does that day cost?
Work done reaches GBP 2,775,000. How much is retained?
Defined Cost rises GBP 100,000. How much Fee goes on top?
Merrow Vale, the Contractor, pays EUR 46,000. Which rate converts it for the Fee?
Source: ECC 11.2(10), 50.7, X7.1, X16.1. Aldermere Contract Data.
Try it
Sort each Aldermere item or firm by the defined term that fits it
Pick a box for each one. Each answer tells you why.
…
Equipment
- Northway's 30 tonne excavator
- The site cabins
Plant and Materials
- Ashvale Precast's culvert box units
- Imported fill for the embankment
Subcontractor
- Cobalt Pumps, which installs the pumps
- Tarnbeck Piling, which installs the piles
Not a Subcontractor
- Kestrel Staffing, paid by the hour
- Northway Plant Hire, the hire firm
Source: ECC 11.2(9), 11.2(14), 11.2(19).
Recap
Find each term's meaning before you use it in a payment
Four habits. Next, follow one payment from cost to cash.
On Monday at work
- Capitals send you to clause 11.2.
- Look up identified terms in your Contract Data.
- Read the definition for your own main Option.
- Ask if an item stays in the works.
In the Toolkit: NEC4 Application for Payment (ECC and ECS, Options A to F) (Excel) Members
Independent course material. It is not published or endorsed by NEC. Clause references are to the NEC4 Engineering and Construction Contract, June 2017 with amendments January 2023. The project and the people are invented. Short quotes from NEC4 (© NEC 2017) and the FIDIC Red Book (© FIDIC 2017) are used for review and comment. Read the full clauses in your own copy of the contract.
Source: ECC 11.1, 11.2(9), 11.2(14). ECC Option C 11.2(31).
Go deeper (optional)
Some items sit between two defined terms
Harder cases. The first two are what-ifs.
Trench sheets left in the ground: Equipment?
ECC 11.2(9), 11.2(14)
A supplier's technician sets up a valve: Subcontractor?
ECC 11.2(19)
What changed from NEC3?
ECC 11.2(10)
Can a Z clause change one?
Option Z
Source: ECC 11.2(9), 11.2(10), 11.2(14), 11.2(19).