Interactive course at Intermediate level
NEC4 Payment and Defined Cost Masterclass
How money moves under the NEC4 ECC, from the first assessment to the final assessment.
Last checked against the contract on 25 October 2026.

Know where every pound in an assessment comes from
Trace any payment
Work out the amount due from the Prices, under each main Option.
Sort any cost
Decide what is Defined Cost and what the Fee covers, component by component.
Price a compensation event
With the full Schedule of Cost Components or the Short Schedule.
Close out the account
Audit the records, then work out the Contractor's share for the final assessment.
The course, module by module
Open a module to see what it covers.
00Key terms and the money mapFree17 min
Lessons
- The words that move money5 min
- From cost to cash6 min
- Who pays whom, and when6 min
- Module check: Key terms and the money map5 min
Clauses
- 11.1
- 11.2
- 11.2(10)
- 11.2(24)
- 11.2(31)
- 44.3
- 50.1
- 50.2
- and 8 more
Terms
identified and defined termsPricesPrice for Work Done to DateDefined CostFeeDisallowed Costamount due
01How the ECC paysFree24 min
Lessons
- The money map7 min
- Six ways to value work5 min
- What counts as Defined Cost6 min
- Why Option C is not cost-plus6 min
- Module check: How the ECC pays5 min
Clauses
- 11.2(10)
- 11.2(31)
- 13.7
- 20.4
- 43.2
- 50.1
- 50.3
- 50.9
- and 8 more
Terms
Defined CostFeeamount duePricesPrice for Work Done to DateActivity ScheduleSchedule of Cost ComponentsDisallowed Cost
02Assessment dates, applications and certificatesMembers23 min
Lessons
- Assessment dates and the applicationAssessment dates and the application6 min
- A late application and the 50.4 capA late application and the 50.4 cap5 min
- Certificates, payment and late paymentCertificates, payment and late payment6 min
- Corrections and interestCorrections and interest6 min
- Module check: Assessment dates, applications and certificatesModule check: Assessment dates, applications and certificates5 min
Clauses
- 12.3
- 13.2
- 13.6
- 13.7
- 50.1
- 50.2
- 50.4
- 50.6
- and 4 more
Terms
assessment dateapplication for paymentcertificateintereststarting dateassessment intervalDefects Certificateamount due
03Retention and the other secondary Options that take money offMembers23 min
Lessons
- What goes on and what comes offWhat goes on and what comes off6 min
- Retention under X16Retention under X165 min
- Delay damages under X7Delay damages under X76 min
- Advance, bonus, KPIs and currenciesAdvance, bonus, KPIs and currencies6 min
- Module check: Retention and the other secondary Options that take money offModule check: Retention and the other secondary Options that take money off5 min
Clauses
- 25.3
- 31.2
- 50.1
- 50.3
- 50.5
- 50.7
- 54.3
- 93.1
- and 7 more
Terms
Option X16delay damagesfirst programmeOption X14Option X20retention free amountCompletionDefects Certificateexchange ratescurrency of the contractfirst programme holdpreliminary shareretention
04Defined Cost, the Fee and the Schedule of Cost ComponentsMembers24 min
Lessons
- Defined Cost is a listDefined Cost is a list6 min
- The price tests in clause 52.1The price tests in clause 52.16 min
- What the Fee carriesWhat the Fee carries6 min
- Sorting one applicationSorting one application6 min
- Module check: Defined Cost, the Fee and the Schedule of Cost ComponentsModule check: Defined Cost, the Fee and the Schedule of Cost Components5 min
Clauses
- 11.2(10)
- 11.2(24)
- 11.2(26)
- 12.3
- 52.1
- 63.1
- 83.2
- X15.5
Terms
Defined CostFeeSchedule of Cost Componentsfee percentageDisallowed CostProvide the WorksEquipmentWorking Areas
05PeopleMembers17 min
Lessons
- Whose cost countsWhose cost counts6 min
- What pay counts and how to share itWhat pay counts and how to share it6 min
- Agency staff, timesheets and bonusesAgency staff, timesheets and bonuses5 min
- Module check: PeopleModule check: People5 min
Clauses
- 11.2(20)
- 11.2(26)
- 11.2(31)
- 16.3
- 52.1
- 52.2
Terms
Defined CostSiteSchedule of Cost ComponentsWorking AreasProvide the WorksDisallowed CostSubcontractornormal place of workingaccrualseverance
06Equipment, Plant and Materials, and ChargesMembers18 min
Lessons
- Pricing EquipmentPricing Equipment6 min
- Plant and Materials, wastage and disposal creditsPlant and Materials, wastage and disposal credits6 min
- Charges, and where each cost goesCharges, and where each cost goes6 min
- Module check: Equipment, Plant and Materials, and ChargesModule check: Equipment, Plant and Materials, and Charges5 min
Clauses
- 11.2(14)
- 70.2
Terms
EquipmentPlant and MaterialsWorking Areasopen market ratetime-related on cost chargespecial Equipmentreasonable availability and utilisationreasonable wastagetime requiredoff-hireconsumed EquipmentCharges
07Subcontractors, design, manufacture and insuranceMembers22 min
Lessons
- Subcontractors and item 41Subcontractors and item 416 min
- Testing a subcontract paymentTesting a subcontract payment5 min
- Design and fabrication away from the SiteDesign and fabrication away from the Site6 min
- Insurance deductionsInsurance deductions5 min
- Module check: Subcontractors, design, manufacture and insuranceModule check: Subcontractors, design, manufacture and insurance5 min
Clauses
- 11.2(19)
- 11.2(26)
- 11.2(31)
- 50.4
- 52.1
- 52.2
Terms
SubcontractorEngineering and Construction Subcontractpricing informationtime barClient's liabilitiesInsurance Tableexcessstanding timefabrication
08The Short Schedule and pricing compensation eventsMembers18 min
Lessons
- Pricing with the Short SchedulePricing with the Short Schedule6 min
- The dividing date and risk allowancesThe dividing date and risk allowances6 min
- Building a quotation: CE007Building a quotation: CE0076 min
- Module check: The Short Schedule and pricing compensation eventsModule check: The Short Schedule and pricing compensation events5 min
Clauses
- 52.1
- 63.1
- 63.2
- 63.8
- 63.9
- 63.14
- 66.3
Terms
Short Schedule of Cost Componentsquotationrisk allowancedividing datePeople Ratesimplementedforecast Defined Costreasonably incurredtime-related costs
09Inflation and the target under Option X1Members18 min
Lessons
- How the Price Adjustment Factor is builtHow the Price Adjustment Factor is built6 min
- Where the adjustment goesWhere the adjustment goes6 min
- The freeze and compensation eventsThe freeze and compensation events6 min
- Module check: Inflation and the target under Option X1Module check: Inflation and the target under Option X15 min
Clauses
- X1.1
- X1.2
- X1.3
- X1.4
- X1.5
Terms
Option X1Price for Work Done to Datetotal of the PricesCompletion Datedividing dateBase Date Index (B)Latest Index (L)
10Disallowed Cost, ground by groundMembers23 min
Lessons
- Test a cost against the listTest a cost against the list5 min
- Grounds that turn on causeGrounds that turn on cause6 min
- Grounds that turn on the kind of costGrounds that turn on the kind of cost6 min
- What Disallowed Cost really costsWhat Disallowed Cost really costs6 min
- Module check: Disallowed Cost, ground by groundModule check: Disallowed Cost, ground by ground5 min
Clauses
- 11.2(10)
- 11.2(26)
- 15.1
- 51.1
- 52.1
- 54.2
- 61.5
- 63.9
- and 1 more
Terms
Disallowed Costshare rangeDefined Costearly warningDefectCompletionconstraintstanding timemarket benchmark
11Records, audits and clawbackMembers23 min
Lessons
- Keep the records and test a sampleKeep the records and test a sample5 min
- Correct a certificate and carry the proofCorrect a certificate and carry the proof6 min
- Close off a part under clause 50.9Close off a part under clause 50.96 min
- Test each audit finding against its evidenceTest each audit finding against its evidence6 min
- Module check: Records, audits and clawbackModule check: Records, audits and clawback5 min
Clauses
- 14.2
- 50.6
- 50.9
- 51.1
- 51.3
- 51.4
- 52.4
- 62.6
Terms
clawbackDefined CostDisallowed CostinterestdelegateDispute Reference Tablefinal assessmentconclusive evidenceaccrualsampleburden of proof
12The Contractor's share and the final accountMembers23 min
Lessons
- What moves the target and what forecasts doWhat moves the target and what forecasts do5 min
- Work out the Contractor's shareWork out the Contractor's share6 min
- The final assessment and what follows a terminationThe final assessment and what follows a termination6 min
- Build the final amount due and the final paymentBuild the final amount due and the final payment6 min
- Module check: The Contractor's share and the final assessmentModule check: The Contractor's share and the final assessment5 min
Clauses
- 20.4
- 36.3
- 53.2
- 53.3
- 54.1
- 54.4
- 63.13
- X7.1
- and 1 more
Terms
Contractor's shareDefects Certificateconclusive evidencetotal of the PricesPrice for Work Done to Dateshare rangefinal assessmenttermination certificatepreliminary sharetargetincrementfinal payment
13Audit one Aldermere assessment40 min
Capstone
- Audit one Aldermere assessmentAudit one Aldermere assessment40 min
Pass mark 12 of 16. A pass, with every module finished, opens the course certificate.
14The UK Construction Act and Y(UK)2, optionalMembers18 min
Lessons
- When the Act applies and what Y(UK)2 addsWhen the Act applies and what Y(UK)2 adds6 min
- Notices that stand, and what a missed one costsNotices that stand, and what a missed one costs6 min
- What if: Dana's payment cycles in EnglandWhat if: Dana's payment cycles in England6 min
- Module check: The UK Construction Act and Y(UK)2, optionalModule check: The UK Construction Act and Y(UK)2, optional5 min
Clauses
- 50.2
- 50.4
- 51.1
- 51.2
- W2.2(1)
- W2.3(7)
- Y2.1
- Y2.2
- and 1 more
Terms
Housing Grants, Construction and Regeneration Act 1996Option Y(UK)2due datepay less noticefinal date for paymentpayment noticenotified sumsmash and grab adjudicationScheme for Construction Contracts
Free lessons
Start here. Your progress stays on this device until you make a free account.
Four amounts from the Aldermere account
Every lesson follows the invented Aldermere Flood Relief Scheme. Short side cases cover the other main Options.
An application arrives a day late, and the cap holds this back for four weeks.
An audit of four weeks of costs, worth £702,400, takes this out of Defined Cost.
A storm repair comes off Defined Cost in full, because the Contractor had to insure the event.
The Contractor's share in the final assessment.
People who work on NEC4 accounts
For people on either side of an ECC contract who work on the account or audit it. It also suits cost consultants. It starts from first principles and ends with the borderline questions practitioners argue about.
Clause references are to the NEC4 Engineering and Construction Contract, June 2017 with amendments January 2023. Independent material. It is not published or endorsed by NEC. The project and the people are invented.
Every course and the Toolkit for $25 a month.
See pricing