NEC4 · ECC 11.2(7)
Defects Certificate
The Supervisor's certificate at the end of the defects stage. It lists the notified Defects still not corrected, or says none remain. The final assessment follows within four weeks.
“a list of Defects that the Supervisor has notified before the defects date” (11.2(7))
On the Aldermere project
Defect 2 was corrected on 26 May 2028, so the Defects Certificate was issued that day.
Lessons that teach this
- Correcting Defects and the Defects CertificateCorrecting Defects and the Defects CertificatePractitioner Course · Module 13 · 6 min Members
- Retention under X16Retention under X16Payment and Defined Cost · Module 3 · 5 min Members
- Assessment dates and applicationsAssessment dates and applicationsPractitioner Course · Module 10 · 5 min Members
- Building the amount dueBuilding the amount duePractitioner Course · Module 10 · 5 min Members
- When the final assessment is dueWhen the final assessment is duePractitioner Course · Module 14 · 5 min Members
- Building the final amount dueBuilding the final amount duePractitioner Course · Module 14 · 5 min Members
- Assessment dates and the applicationAssessment dates and the applicationPayment and Defined Cost · Module 2 · 6 min Members
- Advance, bonus, KPIs and currenciesAdvance, bonus, KPIs and currenciesPayment and Defined Cost · Module 3 · 6 min Members
Where you meet it
- Module 8: What compensation events are and how to notify themPractitioner Course
- Module 10: PaymentPractitioner Course
- Module 13: Completion, take over and DefectsPractitioner Course
- Module 14: The final assessment and closing outPractitioner Course
- Module 2: Assessment dates, applications and certificatesPayment and Defined Cost
- Module 3: Retention and the other secondary Options that take money offPayment and Defined Cost
- Module 12: The Contractor's share and the final accountPayment and Defined Cost
- Module 11: Risk, liability and insuranceNEC4 vs FIDIC 2017
- Module 12: Completion, defects and the final accountNEC4 vs FIDIC 2017
- Module 11: Your contract strategyContract Preparation
- Module 2: There are no clarificationsValid compensation events