Interactive course at Intermediate level
NEC4 vs FIDIC 2017
The ECC and the Red Book side by side, on the same scheme.
Last checked against the contract on 25 October 2026.

Work under either contract and know where the two routes part
Match the roles
See which role does each job under each contract.
Keep both sets of clocks
Notices and time bars differ. See each pair side by side.
Value change both ways
Price a compensation event and a Claim on the same facts.
Explain the differences
Brief a client or a team on where the two contracts part.
The course, module by module
Open a module to see what it covers.
01Two contracts, one schemeFree27 min
Lessons
- How the two contracts are built6 min
- Who does what7 min
- Communications that count7 min
- When documents conflict7 min
- Module check: Two contracts, one scheme5 min
Clauses
- 1.1.4
- 1.1.5
- 1.1.6
- 1.1.7
- 1.1.9
- 1.1.13
- 1.1.19
- 1.1.20
- and 63 more
Terms
Red BookEmployerEngineerEngineer's RepresentativeContractor's Representativecompensation eventClaimNoticeassistantProject ManagerContract DataGeneral ConditionsParticular ConditionsSpecificationDrawings
02Starting out and the programmeMembers20 min
Lessons
- How work startsHow work starts5 min
- What the programme must showWhat the programme must show5 min
- When the reply is silenceWhen the reply is silence5 min
- What the programme doesWhat the programme does5 min
- Module check: Starting out and the programmeModule check: Starting out and the programme5 min
Clauses
- 1.3
- 2.1
- 4.20
- 8.1
- 8.3
- 8.5
- 13.4
- 13.7
- and 12 more
Terms
Programmefirst programmeLetter of AcceptancePerformance SecurityCommencement Datecritical pathReviewNo-objectionEmployer's Personnel
03Getting paidMembers24 min
Lessons
- Applying for paymentApplying for payment6 min
- Certificates and payment datesCertificates and payment dates6 min
- Money held backMoney held back6 min
- When payment is lateWhen payment is late6 min
- Module check: Getting paidModule check: Getting paid5 min
Clauses
- 4.3
- 11.2(31)
- 14.3
- 14.6.1
- 14.6.2
- 14.6.3
- 14.7
- 14.8
- and 10 more
Terms
assessment dateInterim Payment CertificateStatementamount duePrice for Work Done to DateRetention Moneyinterestfinancing chargesNotice of intentionretentionprime lending rate
04Early warning and advance warningMembers22 min
Lessons
- Who warns, and of whatWho warns, and of what5 min
- Registers and meetingsRegisters and meetings6 min
- A warning is not a noticeA warning is not a notice5 min
- The price of not warningThe price of not warning6 min
- Module check: Early warning and advance warningModule check: Early warning and advance warning5 min
Clauses
- 1.3
- 3.8
- 4.20
- 8.4
- 11.2(26)
- 13.7
- 15.1
- 15.2
- and 8 more
Terms
early warningadvance warningNotice of ClaimEarly Warning Registerearly warning meetingprogress reportmanagement meetingDisallowed CostContractor's PersonnelWorksSectionContract Price
05Compensation events and ClaimsMembers20 min
Lessons
- Two tests for the groundTwo tests for the ground5 min
- Notices and time barsNotices and time bars5 min
- From notice to decisionFrom notice to decision5 min
- When nobody decidesWhen nobody decides5 min
- Module check: Compensation events and ClaimsModule check: Compensation events and Claims5 min
Clauses
- 1.1.85
- 1.3
- 3.7.3
- 3.7.5
- 4.12
- 4.12.1
- 20.1
- 20.2.1
- and 12 more
Terms
compensation eventClaimBase DateNotice of Claimfully detailed ClaimUnforeseeabletime limit for agreementNotice of the Parties' agreement
06Changing the workMembers20 min
Lessons
- Who can change the workWho can change the work5 min
- From instruction to decisionFrom instruction to decision5 min
- Instructions that do not say soInstructions that do not say so5 min
- Pricing first and your own ideasPricing first and your own ideas5 min
- Module check: Changing the workModule check: Changing the work5 min
Clauses
- 3.5
- 11.4
- 13.1
- 13.3.1
- 13.3.2
- 14.3
- 16.2
- 20.2
- and 5 more
Terms
instructiondetailed particularsScopeVariationcompensation eventproposed instructionRequest for ProposalEngineer's DeterminationGoodsPermanent Worksvalue engineering
07Valuing changeMembers20 min
Lessons
- How the ECC values a changeHow the ECC values a change5 min
- Bill rates and new ratesBill rates and new rates5 min
- Cost or Cost Plus ProfitCost or Cost Plus Profit5 min
- Weather and new lawsWeather and new laws5 min
- Module check: Valuing changeModule check: Valuing change5 min
Clauses
- 1.1.19
- 1.1.20
- 12.2
- 12.3
- 20.2
- 20.2.1
- 52.1
- 60.1(13)
- and 5 more
Terms
Defined CostCostdividing dateBill of QuantitiesFeeCost Plus Profitexceptionally adverse climatic conditionsContractor's sharefixed rate itemprovisional rate
08Extending time and delay damagesMembers20 min
Lessons
- What adds timeWhat adds time5 min
- Measuring delay and speeding upMeasuring delay and speeding up5 min
- Delay damagesDelay damages5 min
- Getting delay damages paidGetting delay damages paid5 min
- Module check: Extending time and delay damagesModule check: Extending time and delay damages5 min
Clauses
- 3.7.3
- 3.7.4
- 8.8
- 20.2.1
- 20.2.4
- 20.2.7
- 36.3
- 50.3
- and 3 more
Terms
delay damagesCompletion DateTime for CompletionExtension of Timeplanned Completionconcurrent delayDelay DamagesDate of Completion
09Subcontracting and securityMembers20 min
Lessons
- Who counts as a SubcontractorWho counts as a Subcontractor5 min
- Getting a Subcontractor approvedGetting a Subcontractor approved5 min
- Security for the employing PartySecurity for the employing Party5 min
- Advance paymentAdvance payment5 min
- Module check: Subcontracting and securityModule check: Subcontracting and security5 min
Clauses
- 1.1.78
- 2.1
- 4.2
- 4.2.1
- 4.2.2
- 5.1
- 11.2(19)
- 13.3
- and 16 more
Terms
SubcontractorProvide the WorksWorking AreasOption X13Option X14Performance SecurityAccepted Contract AmountProvisional Sumnominated Subcontractoramount due on termination
10Design, quality and testingMembers15 min
Lessons
- Who designs and how a design is clearedWho designs and how a design is cleared5 min
- Tests, searches and failed workTests, searches and failed work5 min
- Quality systems and Tests on CompletionQuality systems and Tests on Completion5 min
- Module check: Design, quality and testingModule check: Design, quality and testing5 min
Clauses
- 4.1
- 4.9.1
- 7.3
- 7.4
- 7.5
- 9.1
- 9.2
- 10.1
- and 12 more
Terms
ScopeDefectSupervisorEquipmentperiod for replyReviewNo-objectionquality planContractor's DocumentsTemporary WorksEmployer's PersonnelQM SystemTests on CompletionCompliance Verification System
11Risk, liability and insuranceMembers15 min
Lessons
- Who carries the riskWho carries the risk5 min
- Claims from others and limits of liabilityClaims from others and limits of liability5 min
- Insurance and when care passesInsurance and when care passes5 min
- Module check: Risk, liability and insuranceModule check: Risk, liability and insurance5 min
Clauses
- 1.15
- 15.1
- 17.1
- 17.2
- 17.6
- 19.1
- 19.2.1
- 19.2.4
- and 11 more
Terms
Client's liabilitiesContractor's liabilitiesOthersInsurance TableDefects CertificateUnforeseeableExceptional EventAccepted Contract AmountWorksindemnity
12Completion, defects and the final accountMembers20 min
Lessons
- Completion and taking overCompletion and taking over5 min
- Defects and the closing certificateDefects and the closing certificate5 min
- Retention and the final paymentRetention and the final payment5 min
- When the final figure is fixedWhen the final figure is fixed5 min
- Module check: Completion, defects and the final accountModule check: Completion, defects and the final account5 min
Clauses
- 1.1.27
- 1.1.88
- 10.1
- 11.1
- 11.2
- 11.2(2)
- 11.9
- 14.12
- and 13 more
Terms
CompletionDefects Notification PeriodTaking-Over Certificatedefects dateDefects CertificatePerformance Certificatefinal assessmentFinal Payment CertificateStatement at completionFinal Statement
13Termination and Exceptional EventsMembers20 min
Lessons
- Terminating for defaultTerminating for default5 min
- Convenience and what each Party is paidConvenience and what each Party is paid5 min
- Prevention and Exceptional EventsPrevention and Exceptional Events5 min
- Ending the contract after a long stoppageEnding the contract after a long stoppage5 min
- Module check: Termination and Exceptional EventsModule check: Termination and Exceptional Events5 min
Clauses
- 8.10
- 15.1
- 15.2.1
- 15.2.2
- 15.5
- 16.2.1
- 16.2.2
- 18.2
- and 12 more
Terms
Termination Tabletermination certificateContract DateNotice to CorrectExceptional EventPerformance SecurityInterim Payment CertificateCost Plus ProfitNotice of intentionprevented obligationsPreventionOption X11
14DisputesMembers20 min
Lessons
- Who decides and when a dispute startsWho decides and when a dispute starts5 min
- The first step and the referralThe first step and the referral5 min
- What a decision does and how to challenge itWhat a decision does and how to challenge it5 min
- Missed limits and the Aldermere resultMissed limits and the Aldermere result5 min
- Module check: DisputesModule check: Disputes5 min
Clauses
- 3.7.5
- 21.1
- 21.4.1
- 21.4.3
- 21.4.4
- W1.1
- W1.1(1)
- W1.2
- and 3 more
Terms
DisputeAdjudicatorDAABSenior RepresentativesNotice of Dissatisfactionnotice of adjudicationtribunalfinal and bindinglist of issuesICC
Free lessons
Start here. Your progress stays on this device until you make a free account.
The same scheme, let twice
The Aldermere Flood Relief Scheme is let under the ECC and under the Red Book. The same things happen on site under both.
The Red Book judges the ground at the Base Date, 84 days before the ECC's test date.
The buried concrete adds this to the Prices under the ECC.
The Red Book adds this to the Contract Price, because Sub-Clause 4.12.4 gives Cost with no profit.
A change to the embankment ends in two decisions on the same figures, six weeks apart.
People who know one form and now work under the other
For practitioners who know one of the two forms and now work under the other. It also suits anyone who has to explain the differences to a client or a team.
Red Book references follow the 2017 text as first published. The course says where to check the 2022 reprint.
Clause references are to the NEC4 Engineering and Construction Contract (June 2017 with amendments January 2023) and the FIDIC Conditions of Contract for Construction, Second Edition 2017 as first published. Independent material. It is not published or endorsed by NEC or FIDIC. The project and the people are invented.
Every course and the Toolkit for $25 a month.
See pricing