Cost
Expenditure the Contractor reasonably incurs in performing the contract, including overheads but not profit. Each Sub-Clause says whether it pays Cost or Cost Plus Profit.
“all expenditure reasonably incurred (or to be incurred) by the Contractor” (FIDIC 1.1.19)
On the Aldermere project
Claim 1's Cost of GBP 76,500 is the GBP 73,153.15 ECC Defined Cost plus GBP 3,346.85 of overheads.
Lessons that teach this
- Cost or Cost Plus ProfitCost or Cost Plus ProfitNEC4 vs FIDIC 2017 · Module 7 · 5 min Members
- Bill rates and new ratesBill rates and new ratesNEC4 vs FIDIC 2017 · Module 7 · 5 min Members
- Weather and new lawsWeather and new lawsNEC4 vs FIDIC 2017 · Module 7 · 5 min Members
- How the two contracts are builtNEC4 vs FIDIC 2017 · Module 1 · 6 min Free
- Who does whatNEC4 vs FIDIC 2017 · Module 1 · 7 min Free
- From notice to decisionFrom notice to decisionNEC4 vs FIDIC 2017 · Module 5 · 5 min Members
- Prevention and Exceptional EventsPrevention and Exceptional EventsNEC4 vs FIDIC 2017 · Module 13 · 5 min Members
Where you meet it
- Module 7: Valuing changeNEC4 vs FIDIC 2017