NEC4 vs FIDIC 2017 · Module 1 · Lesson 1 of 4
How the two contracts are built
Why it matters
On 5 January 2026 one flood scheme is signed twice, under two contracts
One job, let twice. See how each is built.
Source: ECC 11.2(4), X7.1. FIDIC 1.6, 8.8.
The rule
The ECC is built from Options, the Red Book amends one text
One adds chosen layers. The other edits a fixed text.
ECC: core plus Options
Nine sections
Main Option
Disputes
Secondary
Red Book: text plus changes
21 Clauses
Dates and amounts
Changes
Source: ECC Contract Data part one. ECC Z1.1. FIDIC 1.1.9, 1.1.12, 1.1.75.
The rule
One printed Red Book, changed only through its Particular Conditions
Read Part B first: it rewrites printed words.
“these General Conditions as amended by the Particular Conditions” (FIDIC 1.1.9)
21 Clauses
Contract Data: dates, amounts
Special Provisions rewrite printed words
Contract Agreement, Letters, Specification and more
Source: FIDIC 1.1.9, 1.1.10, 1.1.12, 1.1.59, 1.1.75.
The rule
Most ECC terms have a Red Book partner, but few pairs match exactly
Tap each tab. The pairs are close, not exact, so check the clause first.
| Topic | ECC | Red Book |
|---|---|---|
| Pays for the work | Client | EmployerSub-Clause 1.1.31 |
| Runs the contract | Project Manager | EngineerSub-Clause 1.1.35 |
| Inspects the work | Supervisor | Engineer’s Representative or an assistantSub-Clause 3.3 |
| Decides disputes | AdjudicatorClause W1.2 | DAABSub-Clause 1.1.22 |
| Topic | ECC | Red Book |
|---|---|---|
| What to build | ScopeClause 11.2(16) | Specification and DrawingsSub-Clauses 1.1.76, 1.1.30 |
| The ground | Site InformationClause 11.2(18) | Site data the Employer makes availableSub-Clause 2.5 |
| How it is priced | Activity Schedule, a lump sum for each activityClause 11.2(21) | Bill of Quantities, rates for measured workSub-Clause 1.1.5 |
| The price | the PricesClause 11.2(32) | the Contract PriceSub-Clause 1.1.13 |
| Paying for change | Defined Cost plus the FeeClause 11.2(24) | Cost, Cost Plus Profit or ratesSub-Clauses 1.1.19, 1.1.20 |
| Topic | ECC | Red Book |
|---|---|---|
| Judging what was foreseeable | Contract DateClause 11.2(4) | Base DateSub-Clause 1.1.4 |
| The start | starting date | Commencement DateSub-Clause 1.1.7 |
| The finish | Completion DateClause 11.2(3) | Time for Completion, in daysSub-Clause 1.1.84 |
| The work is done | CompletionClause 11.2(2) | Taking over, on the Date of CompletionSub-Clause 1.1.24 |
| The plan | Accepted ProgrammeClause 11.2(1) | ProgrammeSub-Clause 1.1.66 |
| Topic | ECC | Red Book |
|---|---|---|
| A problem ahead | early warningClause 15.1 | advance warningSub-Clause 8.4 |
| More time or money | compensation eventClause 60.1 | Claim, or a VariationSub-Clauses 1.1.6, 1.1.86 |
| Defects stop | defects date | End of the Defects Notification PeriodSub-Clause 1.1.27 |
| Last certificate | Defects CertificateClause 11.2(7) | Performance CertificateSub-Clause 1.1.62 |
Source: ECC 11.2(1) to 11.2(32), 15.1, 60.1, W1.2. FIDIC 1.1.4 to 1.1.86, 2.5, 3.3, 8.4.
See it on the project
At Aldermere the price and dates match, but each contract is built differently
Same money, same dates.
| Topic | ECC | Red Book |
|---|---|---|
| Printing | June 2017 with amendments January 2023 | 2017 as first published. FIDIC reissued it in 2022 |
| How it is built | Option C and Option W1, with X7 and X16. No Option Z | Bill of Quantities. No Sub-Clause in this course is changed |
| Price at the start | GBP 8,400,000, the total of the Prices | Accepted Contract Amount GBP 8,400,000 |
| Foreseeability judged at | Contract Date 5 January 2026 | Base Date 13 October 2025, 28 days before tenders were due |
| Start and finish | 12 January 2026 to the Completion Date, 30 April 2027 | 12 January 2026, then 473 days to 30 April 2027 |
Decide first
Owen Hale, the Contractor’s Representative, needs the Red Book delay damages rate. Is 8.8 enough?
FIDIC 1.1.75, 8.8
Leila Moss, the Contractor’s commercial manager, finds no ECC delay damages cap. Missed one?
ECC X7.1, Z1.1
Source: ECC Contract Data part one, X7.1, Z1.1. FIDIC 1.1.1, 1.1.4, 1.1.12, 1.1.75, 1.1.84, 8.1, 8.8.
Try it
Sort each item into the part of the contract that holds it
Hint: details and dates go in a Contract Data. Changes to printed words go in Option Z or Part B.
…
ECC Contract Data
- ECC. The two week period for reply of Aldermere Water, the Client.
- ECC. The key persons of Merrow Vale Civils, the Contractor, and their jobs.
ECC Option Z
- ECC. A new clause that changes a printed core clause.
Red Book Part A
- Red Book. The Time for Completion of 473 days.
- Red Book. The portal as the system for electronic Notices.
Red Book Part B
- Red Book. New wording for a printed Sub-Clause.
Source: ECC 13.3, 24.1, Z1.1. FIDIC 1.1.12, 1.1.75, 1.1.84, 1.3.
Recap
Before relying on a clause, check the printing and what changes it
Ten minutes now saves a wrong reading.
On Monday at work
- ECC: read Contract Data part one first, for the printing and Options.
- Red Book: read Part B before trusting a printed Sub-Clause (1.1.75).
- Fill the Contract Checklists from each Contract Data: rates, caps (X7.1, 8.8).
In the Toolkit: NEC4 Contract Checklists (ECC and ECS) (Excel) Members
Independent course material. It is not published or endorsed by NEC or FIDIC. Clause references are to the NEC4 Engineering and Construction Contract (June 2017 with amendments January 2023) and the FIDIC Conditions of Contract for Construction, Second Edition 2017 as first published. The project and the people are invented. Short quotes from NEC4 (© NEC 2017) and the FIDIC Red Book (© FIDIC 2017) are used for review and comment. Read the full clauses in your own copy of the contract.
Source: ECC Contract Data part one, X7.1, Z1.1. FIDIC 1.1.9, 1.1.75, 8.8.
Go deeper (optional)
Dates, terms and printings hold a few traps
Harder points. Open a card when you want them.
Contract Date or Base Date?
ECC 11.2(4). FIDIC 1.1.4
Spotting a defined term
ECC 11.1
Recording a change to the ECC
ECC 12.3, 12.4
Which Red Book printing?
FIDIC 1.1.9
Source: ECC 11.1, 11.2(4), 12.3, 12.4. FIDIC 1.1.4, 1.1.9.