Waleed Tariq Academy homeNEC4 vs FIDIC 2017 · How the two contracts are built
Start

NEC4 vs FIDIC 2017 · Module 1 · Lesson 1 of 4

How the two contracts are built

7 screensAbout 6 minutes

Why it matters

On 5 January 2026 one flood scheme is signed twice, under two contracts

One job, let twice. See how each is built.

ECCJune 2017, amended January 2023
Red Book2017, as first published
Delay costs GBP 4,000 a day in both. Where is that rate kept, and what changes it?

Source: ECC 11.2(4), X7.1. FIDIC 1.6, 8.8.

The rule

The ECC is built from Options, the Red Book amends one text

One adds chosen layers. The other edits a fixed text.

ECC: core plus Options

Core clauses

Nine sections

Main Option

Disputes

and

Secondary

Red Book: text plus changes

21 Clauses

Dates and amounts

Part B

Changes

Source: ECC Contract Data part one. ECC Z1.1. FIDIC 1.1.9, 1.1.12, 1.1.75.

The rule

One printed Red Book, changed only through its Particular Conditions

Read Part B first: it rewrites printed words.

“these General Conditions as amended by the Particular Conditions” (FIDIC 1.1.9)

21 Clauses

Part A

: dates, amounts

Particular ConditionsPart B

Special Provisions rewrite printed words

Other documents

Contract Agreement, Letters, Specification and more

Source: FIDIC 1.1.9, 1.1.10, 1.1.12, 1.1.59, 1.1.75.

The rule

Most ECC terms have a Red Book partner, but few pairs match exactly

Tap each tab. The pairs are close, not exact, so check the clause first.

TopicECCRed Book
Pays for the workSub-Clause 1.1.31
Runs the contractSub-Clause 1.1.35
Inspects the work or an Sub-Clause 3.3
Decides disputesClause W1.2Sub-Clause 1.1.22
TopicECCRed Book
What to buildClause 11.2(16) and Sub-Clauses 1.1.76, 1.1.30
The groundClause 11.2(18)Site data the Employer makes availableSub-Clause 2.5
How it is priced, a lump sum for each activityClause 11.2(21), rates for measured workSub-Clause 1.1.5
The priceClause 11.2(32)the Sub-Clause 1.1.13
Paying for change plus the Clause 11.2(24), or ratesSub-Clauses 1.1.19, 1.1.20
TopicECCRed Book
Judging what was foreseeableClause 11.2(4)Sub-Clause 1.1.4
The startSub-Clause 1.1.7
The finishClause 11.2(3), in daysSub-Clause 1.1.84
The work is doneClause 11.2(2)Taking over, on the Sub-Clause 1.1.24
The planClause 11.2(1)Sub-Clause 1.1.66
TopicECCRed Book
A problem aheadClause 15.1Sub-Clause 8.4
More time or moneyClause 60.1, or a Sub-Clauses 1.1.6, 1.1.86
Defects stopEnd of the Sub-Clause 1.1.27
Last certificateClause 11.2(7)Sub-Clause 1.1.62

Source: ECC 11.2(1) to 11.2(32), 15.1, 60.1, W1.2. FIDIC 1.1.4 to 1.1.86, 2.5, 3.3, 8.4.

See it on the project

At Aldermere the price and dates match, but each contract is built differently

Same money, same dates.

TopicECCRed Book
PrintingJune 2017 with amendments January 20232017 as first published. FIDIC reissued it in 2022
How it is builtOption C and Option W1, with X7 and X16. No Option ZBill of Quantities. No Sub-Clause in this course is changed
Price at the startGBP 8,400,000, the total of the Prices GBP 8,400,000
Foreseeability judged atContract Date 5 January 2026Base Date 13 October 2025, 28 days before tenders were due
Start and finish12 January 2026 to the Completion Date, 30 April 202712 January 2026, then 473 days to 30 April 2027

Decide first

Owen Hale, the , needs the Red Book delay damages rate. Is 8.8 enough?

No. The rate and the cap sit in Part A, the Contract Data: GBP 4,000 a day, capped at GBP 840,000. Part B could rewrite 8.8, so he reads that too.

FIDIC 1.1.75, 8.8

Leila Moss, the Contractor’s commercial manager, finds no ECC delay damages cap. Missed one?

No. Option X7 takes the rate from Contract Data part one, GBP 4,000 a day, and sets no maximum. Aldermere adds none, as it has no Option Z.

ECC X7.1, Z1.1

Source: ECC Contract Data part one, X7.1, Z1.1. FIDIC 1.1.1, 1.1.4, 1.1.12, 1.1.75, 1.1.84, 8.1, 8.8.

Try it

Sort each item into the part of the contract that holds it

Hint: details and dates go in a Contract Data. Changes to printed words go in Option Z or Part B.

Item 1 of 6

…

Source: ECC 13.3, 24.1, Z1.1. FIDIC 1.1.12, 1.1.75, 1.1.84, 1.3.

Recap

Before relying on a clause, check the printing and what changes it

Ten minutes now saves a wrong reading.

On Monday at work

  • ECC: read Contract Data part one first, for the printing and Options.
  • : read Part B before trusting a printed Sub-Clause (1.1.75).
  • Fill the Contract Checklists from each Contract Data: rates, caps (X7.1, 8.8).

In the Toolkit: NEC4 Contract Checklists (ECC and ECS) (Excel) Members

Next lesson: Who does what

Your place is kept in this browser. Create a free account to keep it on every device.

Independent course material. It is not published or endorsed by NEC or FIDIC. Clause references are to the NEC4 Engineering and Construction Contract (June 2017 with amendments January 2023) and the FIDIC Conditions of Contract for Construction, Second Edition 2017 as first published. The project and the people are invented. Short quotes from NEC4 (© NEC 2017) and the FIDIC Red Book (© FIDIC 2017) are used for review and comment. Read the full clauses in your own copy of the contract.

Source: ECC Contract Data part one, X7.1, Z1.1. FIDIC 1.1.9, 1.1.75, 8.8.

Go deeper (optional)

Dates, terms and printings hold a few traps

Harder points. Open a card when you want them.

Contract Date or Base Date?

They differ. The Contract Date is the day the ECC was made, 5 January 2026. The Base Date is 28 days before tenders were due, 13 October 2025. Module 5 uses both.

ECC 11.2(4). FIDIC 1.1.4

Spotting a defined term

Defined terms start with capital letters. Terms in italics come from the Contract Data, such as the period for reply.

ECC 11.1

Recording a change to the ECC

Clause 12.4 says “The contract is the entire agreement between the Parties” (12.4). A change the conditions do not provide for needs both Parties to agree it and sign it in writing.

ECC 12.3, 12.4

Which Red Book printing?

FIDIC reissued the 2017 Red Book in 2022 with amendments. This course uses the text as first published, so check the edition your contract names.

FIDIC 1.1.9

Source: ECC 11.1, 11.2(4), 12.3, 12.4. FIDIC 1.1.4, 1.1.9.