Cost Plus Profit

Cost plus the profit percentage in the Contract Data, or 5% if none is stated. It applies only where a Sub-Clause says so.

The contract's words

“Cost plus the applicable percentage for profit stated in the Contract Data” (FIDIC 1.1.20)

On the Aldermere project

The new geotextile rate in Variation 1 is Cost of GBP 10.00 plus 5% profit: GBP 10.50.