Waleed Tariq Academy

Short course at Intermediate level

Is it a valid compensation event?

Which events are compensation events under the NEC4 ECC, and what the Project Manager's reply must say.

6 modules, about 2 h 5 min. 4 free lessons with no account and no card.

Last checked against the contract on 25 October 2026.

A Module 1 lesson screen: A compensation event is an event the contract lists, mostly in clause 60.1

Decide whether an event counts, and give the reason

  • Test the instruction

    Check any instruction against the Scope, whatever its label says.

  • See through clarifications

    Know why NEC has no clarifications, and what that means for a reply.

  • Resolve ambiguities

    Use clause 63.10 when two documents in the Scope disagree.

  • Test the other events

    Apply the tests for ground, weather and late replies, with the eight-week bar.

  • Reply as the Project Manager

    Give the right reason when an event is not a compensation event.

The course, module by module

Open a module to see what it covers.

01Does the instruction change the Scope?Free23 min
02There are no clarificationsMembers16 min

Lessons

  1. Read the words, not the labelRead the words, not the label5 min
  2. What the Supervisor can instructWhat the Supervisor can instruct5 min
  3. Notify the change yourselfNotify the change yourself6 min
  4. Module check: There are no clarificationsModule check: There are no clarifications5 min

Clauses

  • 13.1
  • 13.2
  • 13.7
  • 14.2
  • 14.3
  • 15.1
  • 15.4
  • 27.3
  • and 12 more

Terms

SupervisorScopeinstructioncompensation eventnotificationDefects Certificatetime bardividing date

03Ambiguities and inconsistenciesMembers17 min

Lessons

  1. Spot the clash and notify itSpot the clash and notify it5 min
  2. From the statement to the compensation eventFrom the statement to the compensation event6 min
  3. Who gets the benefit of the doubtWho gets the benefit of the doubt6 min
  4. Module check: Ambiguities and inconsistenciesModule check: Ambiguities and inconsistencies5 min

Clauses

  • 5.12
  • 11.2(15)
  • 12.3
  • 13.2
  • 13.3
  • 13.7
  • 14.1
  • 14.3
  • and 14 more

Terms

ambiguity or inconsistencyScopeorder of precedencephysical conditionsinstructionScope provided by the ClientSite Informationimplementedbed and haunchgranular surround

04The exclusions and the Contractor's designMembers18 min
05The other events people argue aboutMembers26 min

Lessons

  1. Who notifies, and the eight-week barWho notifies, and the eight-week bar6 min
  2. Physical conditions and weatherPhysical conditions and weather7 min
  3. Late replies and withheld acceptancesLate replies and withheld acceptances6 min
  4. The Client, Others and the last resortsThe Client, Others and the last resorts7 min
  5. Module check: The other events people argue aboutModule check: The other events people argue about5 min

Clauses

  • 1.9
  • 13.4
  • 13.8
  • 31.2
  • 31.3
  • 50.5
  • 60.1
  • 60.1(2)
  • and 12 more

Terms

compensation eventSiteSite Informationphysical conditionsweather measurementOthersAccepted Programmetime barlimbmade groundmass concreteten year valuewithhold acceptance

06The reply and the case clinicMembers25 min

Lessons

  1. Reply to a notification in one weekReply to a notification in one week6 min
  2. Price a change before you decide itPrice a change before you decide it6 min
  3. When the reply is silent or wrongWhen the reply is silent or wrong6 min
  4. Run the full test on the case clinicRun the full test on the case clinic7 min
  5. Module check: The reply and the case clinicModule check: The reply and the case clinic5 min

Clauses

  • 1.9
  • 13.3
  • 13.5
  • 60.1
  • 60.1(1)
  • 60.1(5)
  • 60.1(17)
  • 60.1(20)
  • and 11 more

Terms

compensation eventquotationproposed instructiondeemed acceptanceSenior RepresentativesAdjudicatorperiod for replystatement under clause 17.1

Four events on the Aldermere scheme, and why each one counts or not

Every example happens on the invented Aldermere Flood Relief Scheme, with dates that follow the contract's time limits.

£26,085

A portal reply headed "Clarification: no change" turns out to be CE011.

63.10

A drawing and the specification disagree about the outfall pipe bedding. Clause 63.10 decides who gets the benefit of the doubt.

Not a CE

A thicker wet well base slab is not a compensation event, and the Project Manager's reply stands.

CE016

The Supervisor's guardrail direction becomes a compensation event only once the Project Manager instructs it.

People on NEC4 ECC contracts who deal with change

For commercial and project staff on NEC4 ECC contracts, on either side. It also suits cost consultants and auditors who check compensation events.

Clause references are to the NEC4 Engineering and Construction Contract, June 2017 with amendments January 2023. Independent material. It is not published or endorsed by NEC. The project and the people are invented.

Every course and the Toolkit for $25 a month.

See pricing