NEC4 · ECC 61.3
time bar
A deadline that ends a right if missed. Under ECC 61.3 a compensation event notified over eight weeks after awareness changes nothing, with exceptions. The ECS allows seven weeks.
Also written as
- time bars
Lessons that teach this
- What counts, and who notifiesWhat counts, and who notifiesCase Law · Module 8 · 6 min Members
- Testing an event against the contractTesting an event against the contractPractitioner Course · Module 8 · 5 min Members
- Notifying within eight weeksNotifying within eight weeksPractitioner Course · Module 8 · 5 min Members
- The periods that differThe periods that differPractitioner Course · Module 18 · 6 min Members
- Testing a subcontract paymentTesting a subcontract paymentPayment and Defined Cost · Module 7 · 5 min Members
- Time limits nobody mentionsTime limits nobody mentionsCase Law · Module 2 · 5 min Members
- Notify the change yourselfNotify the change yourselfValid compensation events · Module 2 · 6 min Members
- Who notifies, and the eight-week barWho notifies, and the eight-week barValid compensation events · Module 5 · 6 min Members
Where you meet it
- Module 8: What compensation events are and how to notify themPractitioner Course
- Module 18: What changes in a subcontract under the ECSPractitioner Course
- Module 7: Subcontractors, design, manufacture and insurancePayment and Defined Cost
- Module 2: Mutual trust and co-operationCase Law
- Module 8: What counts as a compensation event, and the time barsCase Law
- Module 2: There are no clarificationsValid compensation events
- Module 5: The other events people argue aboutValid compensation events