NEC4 · ECC 60.1(12)

physical conditions

Conditions within the Site, other than weather, that were too unlikely at the Contract Date for an experienced contractor to price. Only the unforeseeable part counts.

On the Aldermere project

The old concrete foundations found under Station Road on 3 March 2026 were notified as physical conditions under 60.1(12).