NEC4 · ECC 31.2
planned Completion
The date the Contractor's programme shows for Completion. It may be earlier than the Completion Date, a gap often called terminal float. Delay is measured against it.
On the Aldermere project
Merrow Vale's first CE007 quotation delayed planned Completion by 9 days.
Also written as
- terminal float
Lessons that teach this
- What a programme must showWhat a programme must showPractitioner Course · Module 7 · 5 min Members
- Reply, refusal and silenceReply, refusal and silencePractitioner Course · Module 7 · 5 min Members
- Keeping it currentKeeping it currentPractitioner Course · Module 7 · 5 min Members
- Measuring delay and speeding upMeasuring delay and speeding upNEC4 vs FIDIC 2017 · Module 8 · 5 min Members
- What the programme doesWhat the programme doesNEC4 vs FIDIC 2017 · Module 2 · 5 min Members
Where you meet it
- Module 7: The programmePractitioner Course
- Module 6: The programme, prevention and concurrencyCase Law
- Module 8: Extending time and delay damagesNEC4 vs FIDIC 2017