NEC4 · ECC 11.2(14)
Plant and Materials
Items meant to become part of the works, such as pumps or concrete. Kit that is used but not left in the works is Equipment.
“items intended to be included in the works” (11.2(14))
On the Aldermere project
The pumps and controls Cobalt Pumps Ltd installs at Mill Lane are Plant and Materials.
Lessons that teach this
- Plant and Materials, wastage and disposal creditsPlant and Materials, wastage and disposal creditsPayment and Defined Cost · Module 6 · 6 min Members
- Charges, and where each cost goesCharges, and where each cost goesPayment and Defined Cost · Module 6 · 6 min Members
- The Schedule of Cost ComponentsThe Schedule of Cost ComponentsPractitioner Course · Module 11 · 5 min Members
- Disallowed CostDisallowed CostPractitioner Course · Module 11 · 5 min Members
- Who is whoPractitioner Course · Module 1 · 5 min Free
- Defined Cost and the FeeDefined Cost and the FeePractitioner Course · Module 3 · 5 min Members
- Duties beside the workDuties beside the workPractitioner Course · Module 6 · 5 min Members
- Who carries which lossWho carries which lossPractitioner Course · Module 15 · 6 min Members
Where you meet it
- Module 11: Defined Cost, the Schedule of Cost Components and Disallowed CostPractitioner Course
- Module 6: Equipment, Plant and Materials, and ChargesPayment and Defined Cost