NEC4 · ECC 11.2(16)
Scope
Information that describes the works or limits how the Contractor may do them. It sits in documents the Contract Data lists or in an instruction. NEC3 called it Works Information.
“specifies and describes the works” (11.2(16))
On the Aldermere project
Dana's instruction of 1 June 2026 for a flatter embankment slope changed the Scope, so it was a compensation event.
Also written as
- the Scope
- Works Information
Lessons that teach this
- Rankings and the Contractor's ScopeRankings and the Contractor's ScopeCase Law · Module 4 · 5 min Members
- What the Scope doesWhat the Scope doesContract Preparation · Module 7 · 5 min Members
- What the Scope is and who changes itValid compensation events · Module 1 · 6 min Free
- Test the instruction against the ScopeValid compensation events · Module 1 · 6 min Free
- Design and scopeDesign and scopeContract Preparation · Module 2 · 6 min Members
- Spot the clash, then price itSpot the clash, then price itCase Law · Module 4 · 6 min Members
- Read the documents togetherRead the documents togetherCase Law · Module 4 · 5 min Members
- A clarification can still be a changeA clarification can still be a changeCase Law · Module 4 · 5 min Members
Where you meet it
- Module 1: How the ECC fits togetherPractitioner Course · Free
- Module 6: The Contractor's main responsibilitiesPractitioner Course
- Module 4: The documents, the Scope and ambiguitiesCase Law
- Module 6: Changing the workNEC4 vs FIDIC 2017
- Module 10: Design, quality and testingNEC4 vs FIDIC 2017
- Module 2: The procurement questions to answer firstContract Preparation
- Module 7: Drafting Scope and Site Information that avoids argumentContract Preparation
- Module 8: The tender packageContract Preparation
- Module 1: Does the instruction change the Scope?Valid compensation events · Free
- Module 2: There are no clarificationsValid compensation events
- Module 3: Ambiguities and inconsistenciesValid compensation events