NEC4 · ECC 11.2(1)
Accepted Programme
The programme the Project Manager last accepted, or the one named in the Contract Data until then. Each accepted programme replaces the one before it.
“the latest programme accepted by the Project Manager” (11.2(1))
On the Aldermere project
Merrow Vale's resubmitted programme was treated as accepted on 4 March 2026. It became the Accepted Programme used for CE007.
Also written as
- Accepted Programmes
Lessons that teach this
- The dates part one fixesThe dates part one fixesPractitioner Course · Module 2 · 6 min Members
- What a programme must showWhat a programme must showPractitioner Course · Module 7 · 5 min Members
- Keeping it currentKeeping it currentPractitioner Course · Module 7 · 5 min Members
- The programme that countsThe programme that countsCase Law · Module 6 · 6 min Members
- Delay with two causesDelay with two causesCase Law · Module 6 · 6 min Members
- Checking the target and the programmeChecking the target and the programmeContract Preparation · Module 9 · 5 min Members
- Subcontract forms and what to pass downSubcontract forms and what to pass downContract Preparation · Module 9 · 6 min Members
- The tender programmeThe tender programmeContract Preparation · Module 10 · 5 min Members
Where you meet it
- Module 2: The Contract Data, before you signPractitioner Course
- Module 7: The programmePractitioner Course
- Module 6: The programme, prevention and concurrencyCase Law
- Module 8: The tender packageContract Preparation
- Module 9: Tender assessment and subcontractsContract Preparation
- Module 10: The tenderer's viewContract Preparation
- Module 5: The other events people argue aboutValid compensation events