NEC4 · ECC 11.2(6) and 21.2
accepted design
The Contractor's design after the Project Manager accepts it. Work that departs from it is a Defect, and acceptance does not make the Client liable for the design.
Lessons that teach this
- The Contractor's designThe Contractor's designValid compensation events · Module 4 · 6 min Members
- Proposals and savingsProposals and savingsValid compensation events · Module 4 · 6 min Members
Where you meet it
- Module 4: The exclusions and the Contractor's designValid compensation events