NEC4 · ECC 11.2(6)

Defect

Part of the works that does not meet the Scope. For work the Contractor designed, also a part that breaks the applicable law or departs from its accepted design.

The contract's words

“a part of the works which is not in accordance with the Scope” (11.2(6))

On the Aldermere project

Defect 1, the headwall joints, was notified on 18 May 2027 and corrected on 3 June 2027.