NEC4 · ECC 62.6
deemed acceptance
Acceptance the contract treats as given after a Project Manager's silence. The Contractor must first notify the failure to reply, and a further period must pass.
On the Aldermere project
Merrow Vale's resubmitted programme had no reply. After the failure was notified on 25 February, it was treated as accepted on 4 March 2026.
Also written as
- treated as accepted
- treated as acceptance
- deemed accepted
Lessons that teach this
- When a reply is lateWhen a reply is latePractitioner Course · Module 4 · 6 min Members
- Reply, refusal and silenceReply, refusal and silencePractitioner Course · Module 7 · 5 min Members
- Keeping it currentKeeping it currentPractitioner Course · Module 7 · 5 min Members
- Quotations and the replyQuotations and the replyPractitioner Course · Module 9 · 5 min Members
- Delay, and when Dana assessesDelay, and when Dana assessesPractitioner Course · Module 9 · 5 min Members
- Proposed instructions and implementationProposed instructions and implementationPractitioner Course · Module 9 · 5 min Members
- Quotes, replies and silenceQuotes, replies and silenceCase Law · Module 9 · 6 min Members
- Reply to a notification in one weekReply to a notification in one weekValid compensation events · Module 6 · 6 min Members
Where you meet it
- Module 4: Communications and the period for replyPractitioner Course
- Module 7: The programmePractitioner Course
- Module 9: Quoting for and implementing compensation eventsPractitioner Course
- Module 9: Assessing and proving compensation eventsCase Law
- Module 6: The reply and the case clinicValid compensation events