NEC4 · ECC W1.1
Senior Representatives
Senior people each Party names in the Contract Data. Under W1 each side sends them a statement of case, and they have up to three weeks to settle the dispute.
On the Aldermere project
Merrow Vale referred the CE014 dispute to the Senior Representatives on 3 August 2026. Their list of issues followed on 24 August.
Also written as
- Senior Representative
- statement of case
- statements of case
Lessons that teach this
- When the assessment becomes conclusiveWhen the assessment becomes conclusivePractitioner Course · Module 14 · 6 min Members
- Choosing the Option and starting a disputeChoosing the Option and starting a disputePractitioner Course · Module 16 · 5 min Members
- When the reply is silent or wrongWhen the reply is silent or wrongValid compensation events · Module 6 · 6 min Members
- What W2 and W3 changeWhat W2 and W3 changePractitioner Course · Module 16 · 5 min Members
- When the decision is dueWhen the decision is dueCase Law · Module 13 · 5 min Members
- The first step and the referralThe first step and the referralNEC4 vs FIDIC 2017 · Module 14 · 5 min Members
- Missed limits and the Aldermere resultMissed limits and the Aldermere resultNEC4 vs FIDIC 2017 · Module 14 · 5 min Members
- Certificates, payment and late paymentCertificates, payment and late paymentPayment and Defined Cost · Module 2 · 6 min Members
Where you meet it
- Module 14: The final assessment and closing outPractitioner Course
- Module 16: Disputes under W1, W2 and W3Practitioner Course
- Module 13: Disputes under W1 and W3Case Law
- Module 14: DisputesNEC4 vs FIDIC 2017
- Module 6: The reply and the case clinicValid compensation events