Is it a valid compensation event? · Module 1 · Lesson 1 of 4

What a compensation event is

7 screensAbout 5 minutes

Why it matters

Valid events cut Merrow Vale's delay damages from GBP 104,000 to GBP 4,000

Completion came one day late. CE007 and CE014 had moved the Completion Date by 25 days.

No valid events: 26 days late
GBP 104,000
CE007: 7 days
−GBP 28,000
CE014, Project Manager: 12 days
−GBP 48,000
CE014, Adjudicator: 6 days
−GBP 24,000
Paid: 1 day late
GBP 4,000
So what makes an event a , and how do you test one?

Source: ECC 60.1, 63.6, X7.1.

The rule

A compensation event is an event the contract lists, mostly in clause 60.1

Start with the list. An event that is not on it moves nothing, however much it costs.

“The following events are compensation events” (60.1)

21entries in the list in clause 60.1
0added by Aldermere's (60.1(21))

Source: ECC 60.1, 60.1(21).

The rule

A valid event moves the target

The target is the . Inside 10% of it, Merrow Vale keeps half a saving.

For the , changes to the and the dates

“are their only rights in respect of a compensation event” (63.6)

Valid

Target and dates move.

Not valid

Cost paid, target fixed, smaller.

Source: ECC 63.6. ECC Option C 54.1, 54.2.

The rule

Eight questions, taken in order, decide whether an event is valid

Step through them. Stop at the first that ends the matter. This module teaches questions 1 and 3.

Question 1 of 8
QuestionClausesTaught in
1Which listed event is it?60.1Modules 1 and 5This module
2Did someone with the power give it, with effect?13.1, 13.2, 14.2, 14.3Module 2
3Does it change the Scope as it stood just before?11.2(16), 60.1(1)Modules 1 and 2This module
4Did it settle an ambiguity or inconsistency?17.1, 63.10Module 3
5Does an exclusion apply?60.1(1), 45, 46Module 4
6Does every part of its own test hold?60.1(2) to (21), 60.2, 60.3Module 5
7Was it notified in time, and on its own?61.1, 61.3, 61.7, 13.7Modules 2 and 5
8Does it have an effect, and what does the reply say?61.2, 61.4, W1.1Module 6

Questions 3 to 5 are for an that changes . Question 6 is for any other event.

Source: ECC 60.1, 60.1(1), 61.3, 61.4. The map names the rest.

See it on the project

CE011 ran 16 April to 26 May

CE011: a query reply from the required the joints sealed inside. This course covers steps 1 to 3.

This course

  1. The event16 Apr60.1(1)
  2. Notification21 Apr61.3
  3. Reply27 Apr61.4
Practitioner Course

  1. QuotationGBP 26,08562.3
  2. Assessment63.1
  3. Implementation26 May66.1

Source: ECC 60.1(1), 61.3, 61.4, 62.3, 63.1, 66.1.

Quick check · Try it

Two questions on what you have just covered

Raj's request, then the money.

Quick checkPick an answer to see if you are right and why
1Suppose Merrow Vale's excavator breaks down for two days. Raj, its planner, asks its commercial manager Leila to notify a compensation event. What does she say?
Not one, as no listed event covers its own Equipment
Notify it within eight weeks, to keep the event alive
Notify it, but only if it delays Completion
2Suppose Merrow Vale spends GBP 10,000 of Defined Cost on work outside any compensation event. The Fee is 11% and its share 50%. How far does its share fall?
GBP 5,550
GBP 5,000
Nothing, as it is paid as Defined Cost

2 questions to answer

Source: ECC 11.2(10), 60.1. ECC Option C 11.2(31), 54.1.

Recap

Find the event in the list before you argue about money

Three habits that keep a validity argument short.

On Monday at work

  • Find each event in clause 60.1 before anyone prices it.
  • Run the eight questions in order and stop at the first that fails.
  • Log each event in the Compensation Event Register with its 60.1 entry.

In the Toolkit: NEC4 Compensation Event Register (ECC and ECS) (Excel) Members

Next lesson: What the Scope is and who changes it

Your place is kept in this browser. Create a free account to keep it on every device.

Independent course material. It is not published or endorsed by NEC. Clause references are to the NEC4 Engineering and Construction Contract, June 2017 with amendments January 2023. The project and the people are invented. Short quotes from NEC4 (© NEC 2017) and the FIDIC Red Book (© FIDIC 2017) are used for review and comment. Read the full clauses in your own copy of the contract.

Source: ECC 60.1, 63.6.

Go deeper (optional)

Validity cuts both ways, and the list can grow

Three points for later. Skip them if short of time.

Dana, the Project Manager, accepts an event that is not on the list. Who loses?

Aldermere Water. The target and the dates move against the Client, so it pays more and waits longer. Validity cuts both ways.

ECC 63.6

Can the contract add events to the list?

Yes. Options B and D and some secondary Options add more, and Contract Data part one can list others (60.1(21)). Aldermere's contract adds none.

ECC 60.1(21)

What happens after the reply?

Merrow Vale quotes within three weeks and Dana replies within two (62.3). The assessment and the new Prices follow (63, 66). The Practitioner Course covers them.

ECC 62.3, 63.1, 66.1

Source: ECC 60.1(21), 62.3, 63.1, 63.6, 66.1. ECC Option C 54.1.