Is it a valid compensation event? · Module 1 · Lesson 1 of 4
What a compensation event is
Why it matters
Valid events cut Merrow Vale's delay damages from GBP 104,000 to GBP 4,000
Completion came one day late. CE007 and CE014 had moved the Completion Date by 25 days.
Source: ECC 60.1, 63.6, X7.1.
The rule
A compensation event is an event the contract lists, mostly in clause 60.1
Start with the list. An event that is not on it moves nothing, however much it costs.
“The following events are compensation events” (60.1)
Source: ECC 60.1, 60.1(21).
The rule
A valid event moves the target
The target is the total of the Prices. Inside 10% of it, Merrow Vale keeps half a saving.
For the Parties, changes to the Prices and the dates
“are their only rights in respect of a compensation event” (63.6)
Valid
Target and dates move.
Not valid
Cost paid, target fixed, share smaller.
Source: ECC 63.6. ECC Option C 54.1, 54.2.
The rule
Eight questions, taken in order, decide whether an event is valid
Step through them. Stop at the first that ends the matter. This module teaches questions 1 and 3.
| Question | Clauses | Taught in |
|---|---|---|
| 1Which listed event is it? | 60.1 | Modules 1 and 5This module |
| 2Did someone with the power give it, with effect? | 13.1, 13.2, 14.2, 14.3 | Module 2 |
| 3Does it change the Scope as it stood just before? | 11.2(16), 60.1(1) | Modules 1 and 2This module |
| 4Did it settle an ambiguity or inconsistency? | 17.1, 63.10 | Module 3 |
| 5Does an exclusion apply? | 60.1(1), 45, 46 | Module 4 |
| 6Does every part of its own test hold? | 60.1(2) to (21), 60.2, 60.3 | Module 5 |
| 7Was it notified in time, and on its own? | 61.1, 61.3, 61.7, 13.7 | Modules 2 and 5 |
| 8Does it have an effect, and what does the reply say? | 61.2, 61.4, W1.1 | Module 6 |
Questions 3 to 5 are for an instruction that changes the Scope. Question 6 is for any other event.
Source: ECC 60.1, 60.1(1), 61.3, 61.4. The map names the rest.
See it on the project
CE011 ran 16 April to 26 May
CE011: a query reply from the Project Manager required the joints sealed inside. This course covers steps 1 to 3.
- The event16 Apr60.1(1)
- Notification21 Apr61.3
- Reply27 Apr61.4
- QuotationGBP 26,08562.3
- Assessment63.1
- Implementation26 May66.1
Source: ECC 60.1(1), 61.3, 61.4, 62.3, 63.1, 66.1.
Quick check · Try it
Two questions on what you have just covered
Raj's request, then the money.
2 questions to answer
Source: ECC 11.2(10), 60.1. ECC Option C 11.2(31), 54.1.
Recap
Find the event in the list before you argue about money
Three habits that keep a validity argument short.
On Monday at work
- Find each event in clause 60.1 before anyone prices it.
- Run the eight questions in order and stop at the first that fails.
- Log each event in the Compensation Event Register with its 60.1 entry.
In the Toolkit: NEC4 Compensation Event Register (ECC and ECS) (Excel) Members
Independent course material. It is not published or endorsed by NEC. Clause references are to the NEC4 Engineering and Construction Contract, June 2017 with amendments January 2023. The project and the people are invented. Short quotes from NEC4 (© NEC 2017) and the FIDIC Red Book (© FIDIC 2017) are used for review and comment. Read the full clauses in your own copy of the contract.
Source: ECC 60.1, 63.6.
Go deeper (optional)
Validity cuts both ways, and the list can grow
Three points for later. Skip them if short of time.
Dana, the Project Manager, accepts an event that is not on the list. Who loses?
ECC 63.6
Can the contract add events to the list?
ECC 60.1(21)
What happens after the reply?
ECC 62.3, 63.1, 66.1
Source: ECC 60.1(21), 62.3, 63.1, 63.6, 66.1. ECC Option C 54.1.