NEC4 · ECC 60.1(13)

weather measurement

A monthly weather record taken at the place the Contract Data names. A value rarer than once in ten years, judged on the weather data, is a compensation event.

On the Aldermere project

Aldermere's weather is recorded at a station 3 km from the embankment.