NEC4 · ECC Option C 54.1 (Option D 54.5)
Contractor's share
Under Options C and D, the Contractor's part of any saving or overrun against the target. It is assessed at Completion and again in the final assessment.
On the Aldermere project
The final saving of GBP 272,000 fell in the 90% to 110% range, so Merrow Vale's share was GBP 136,000.
Also written as
- pain and gain
- gain share
Lessons that teach this
- The Contractor's shareThe Contractor's sharePractitioner Course · Module 3 · 6 min Members
- The Contractor's shareThe Contractor's sharePractitioner Course · Module 12 · 5 min Members
- What moves the target and what forecasts doWhat moves the target and what forecasts doPayment and Defined Cost · Module 12 · 5 min Members
- The target and the paymentThe target and the paymentPractitioner Course · Module 3 · 5 min Members
- The target and what moves itThe target and what moves itPractitioner Course · Module 12 · 5 min Members
- Building the final amount dueBuilding the final amount duePractitioner Course · Module 14 · 5 min Members
- The share waits for CompletionThe share waits for CompletionCase Law · Module 10 · 5 min Members
- Proposals and savingsProposals and savingsValid compensation events · Module 4 · 6 min Members
Where you meet it
- Module 3: How Option C pays youPractitioner Course
- Module 12: Target contracts under Options C and DPractitioner Course
- Module 14: The final assessment and closing outPractitioner Course
- Module 12: The Contractor's share and the final accountPayment and Defined Cost
- Module 10: Payment, Defined Cost and the shareCase Law
- Module 7: Valuing changeNEC4 vs FIDIC 2017
- Module 4: The exclusions and the Contractor's designValid compensation events