NEC4 · ECC 62.2
quotation
The Contractor's priced offer for a compensation event. It proposes the change to the Prices and how far the Completion Date and each Key Date should move.
On the Aldermere project
Merrow Vale's first CE007 quotation, on 30 March 2026, was GBP 86,400 and 9 days of delay to planned Completion.
Also written as
- quotations
- revised quotation
- revised quotations
Lessons that teach this
- Quotations and the replyQuotations and the replyPractitioner Course · Module 9 · 5 min Members
- Building a quotation: CE007Building a quotation: CE007Payment and Defined Cost · Module 8 · 6 min Members
- What a missed warning costsWhat a missed warning costsPractitioner Course · Module 5 · 6 min Members
- The reply and what silence meansThe reply and what silence meansPractitioner Course · Module 8 · 5 min Members
- Building the change to the PricesBuilding the change to the PricesPractitioner Course · Module 9 · 5 min Members
- Delay, and when Dana assessesDelay, and when Dana assessesPractitioner Course · Module 9 · 5 min Members
- Proposed instructions and implementationProposed instructions and implementationPractitioner Course · Module 9 · 5 min Members
- Pricing with the Short SchedulePricing with the Short SchedulePayment and Defined Cost · Module 8 · 6 min Members
Where you meet it
- Module 5: Early warningsPractitioner Course
- Module 8: What compensation events are and how to notify themPractitioner Course
- Module 9: Quoting for and implementing compensation eventsPractitioner Course
- Module 8: The Short Schedule and pricing compensation eventsPayment and Defined Cost
- Module 9: Assessing and proving compensation eventsCase Law
- Module 6: The reply and the case clinicValid compensation events