NEC4 · ECC 13.3
period for reply
The time the Contract Data gives for replying to a communication, unless a clause sets its own time. It can be extended by agreement before the reply is due.
On the Aldermere project
Aldermere's period for reply is two weeks. For the wet well design it was extended by agreement on 19 March 2026 to 1 April.
Also written as
- periods for reply
Lessons that teach this
- The period for replyThe period for replyPractitioner Course · Module 4 · 5 min Members
- When a communication countsWhen a communication countsPractitioner Course · Module 4 · 6 min Members
- When a submission is not acceptedWhen a submission is not acceptedPractitioner Course · Module 4 · 6 min Members
- Two parts and who fills them inTwo parts and who fills them inPractitioner Course · Module 2 · 5 min Members
- Replies, acceptance and delegationReplies, acceptance and delegationCase Law · Module 3 · 6 min Members
- Who designs and how a design is clearedWho designs and how a design is clearedNEC4 vs FIDIC 2017 · Module 10 · 5 min Members
- The clocks in part oneThe clocks in part oneContract Preparation · Module 6 · 6 min Members
- Reply to a notification in one weekReply to a notification in one weekValid compensation events · Module 6 · 6 min Members
Where you meet it
- Module 2: The Contract Data, before you signPractitioner Course
- Module 4: Communications and the period for replyPractitioner Course
- Module 3: Communications and the Project ManagerCase Law
- Module 10: Design, quality and testingNEC4 vs FIDIC 2017
- Module 6: The Contract Data entries that cause trouble laterContract Preparation
- Module 6: The reply and the case clinicValid compensation events