NEC4 · ECC 63.1
dividing date
The date that splits a compensation event's cost into actual Defined Cost before it and forecast Defined Cost after it. It is the date of the triggering instruction or notification.
On the Aldermere project
CE007's dividing date is 6 March 2026: actual Defined Cost GBP 6,153.15 and forecast GBP 67,000.00.
Also written as
- dividing dates
Lessons that teach this
- The dividing date and risk allowancesThe dividing date and risk allowancesPayment and Defined Cost · Module 8 · 6 min Members
- The dividing date and the recordsThe dividing date and the recordsCase Law · Module 9 · 6 min Members
- How the ECC values a changeHow the ECC values a changeNEC4 vs FIDIC 2017 · Module 7 · 5 min Members
- Keeping it currentKeeping it currentPractitioner Course · Module 7 · 5 min Members
- Building the change to the PricesBuilding the change to the PricesPractitioner Course · Module 9 · 5 min Members
- Delay, and when Dana assessesDelay, and when Dana assessesPractitioner Course · Module 9 · 5 min Members
- The freeze and compensation eventsThe freeze and compensation eventsPayment and Defined Cost · Module 9 · 6 min Members
- The programme that countsThe programme that countsCase Law · Module 6 · 6 min Members
Where you meet it
- Module 7: The programmePractitioner Course
- Module 9: Quoting for and implementing compensation eventsPractitioner Course
- Module 8: The Short Schedule and pricing compensation eventsPayment and Defined Cost
- Module 9: Inflation and the target under Option X1Payment and Defined Cost
- Module 6: The programme, prevention and concurrencyCase Law
- Module 9: Assessing and proving compensation eventsCase Law
- Module 7: Valuing changeNEC4 vs FIDIC 2017
- Module 2: There are no clarificationsValid compensation events