delay damages
Under Option X7, a fixed daily sum the Contractor pays for each day Completion, or earlier take over, falls after the Completion Date.
On the Aldermere project
Completion came one day late on 26 May 2027, so GBP 4,000 of delay damages was deducted.
Lessons that teach this
- Delay damagesDelay damagesNEC4 vs FIDIC 2017 · Module 8 · 5 min Members
- Getting delay damages paidGetting delay damages paidNEC4 vs FIDIC 2017 · Module 8 · 5 min Members
- Delay damages and qualityDelay damages and qualityPractitioner Course · Module 13 · 5 min Members
- Delay damages under X7Delay damages under X7Payment and Defined Cost · Module 3 · 6 min Members
- Delay damagesDelay damagesContract Preparation · Module 5 · 6 min Members
- A rate that holds upA rate that holds upCase Law · Module 12 · 6 min Members
- Which days countWhich days countCase Law · Module 12 · 7 min Members
- Completion, Key Dates and take overCompletion, Key Dates and take overPractitioner Course · Module 13 · 5 min Members
Where you meet it
- Module 13: Completion, take over and DefectsPractitioner Course
- Module 3: Retention and the other secondary Options that take money offPayment and Defined Cost
- Module 12: Delay damages, bonds and terminationCase Law
- Module 8: Extending time and delay damagesNEC4 vs FIDIC 2017