NEC4 · ECC 31.1
first programme
The programme due by the Contract Data deadline when none is identified. Until a complete one is submitted, a quarter of the Price for Work Done to Date is retained.
On the Aldermere project
At the first assessment date, 9 February 2026, GBP 78,000 was retained, a quarter of the GBP 312,000 Price for Work Done to Date.
Also written as
- first programmes
Lessons that teach this
- What a programme must showWhat a programme must showPractitioner Course · Module 7 · 5 min Members
- What goes on and what comes offWhat goes on and what comes offPayment and Defined Cost · Module 3 · 6 min Members
- How work startsHow work startsNEC4 vs FIDIC 2017 · Module 2 · 5 min Members
- What the programme must showWhat the programme must showNEC4 vs FIDIC 2017 · Module 2 · 5 min Members
- What the programme doesWhat the programme doesNEC4 vs FIDIC 2017 · Module 2 · 5 min Members
- The clocks in part oneThe clocks in part oneContract Preparation · Module 6 · 6 min Members
Where you meet it
- Module 7: The programmePractitioner Course
- Module 3: Retention and the other secondary Options that take money offPayment and Defined Cost
- Module 2: Starting out and the programmeNEC4 vs FIDIC 2017