defects date
The end of the period after Completion in which Defects are notified. The Contract Data sets how many weeks after Completion it falls.
On the Aldermere project
Completion was on 26 May 2027, so the defects date, 52 weeks later, is 24 May 2028.
Lessons that teach this
- Defects and the defects dateDefects and the defects dateCase Law · Module 5 · 6 min Members
- Correcting Defects and the Defects CertificateCorrecting Defects and the Defects CertificatePractitioner Course · Module 13 · 6 min Members
- Design or build, and who insuresDesign or build, and who insuresCase Law · Module 5 · 6 min Members
- Defects and the closing certificateDefects and the closing certificateNEC4 vs FIDIC 2017 · Module 12 · 5 min Members
- Key Dates, take over and DefectsKey Dates, take over and DefectsContract Preparation · Module 6 · 5 min Members
- Who is whoPractitioner Course · Module 1 · 5 min Free
- The dates part one fixesThe dates part one fixesPractitioner Course · Module 2 · 6 min Members
- How the two contracts are builtNEC4 vs FIDIC 2017 · Module 1 · 6 min Free
Where you meet it
- Module 13: Completion, take over and DefectsPractitioner Course
- Module 5: Design, Defects and insuranceCase Law
- Module 12: Completion, defects and the final accountNEC4 vs FIDIC 2017
- Module 6: The Contract Data entries that cause trouble laterContract Preparation