Defects Notification Period

The period after the Date of Completion for notifying defects, one year unless the Contract Data says otherwise. Sub-Clause 11.3 allows it to be extended.

The contract's words

“the period for notifying defects and/or damage in the Works” (FIDIC 1.1.27)

On the Aldermere project

The DNP ran 365 days from 26 May 2027, ending 25 May 2028.