NEC4 · ECC Option C 11.2(26)
Disallowed Cost
Cost the Project Manager removes from Defined Cost, such as cost not backed by records or caused by a missed early warning. It is left out of the amount due.
“is not justified by the Contractor’s accounts and records” (11.2(26))
On the Aldermere project
Dana's check of the four weeks to 29 June 2026 found Disallowed Cost of GBP 10,000.
Lessons that teach this
- Disallowed CostDisallowed CostPractitioner Course · Module 11 · 5 min Members
- What Disallowed Cost really costsWhat Disallowed Cost really costsPayment and Defined Cost · Module 10 · 6 min Members
- Test a cost against the listTest a cost against the listPayment and Defined Cost · Module 10 · 5 min Members
- Defined Cost and the FeeDefined Cost and the FeePractitioner Course · Module 11 · 5 min Members
- The Schedule of Cost ComponentsThe Schedule of Cost ComponentsPractitioner Course · Module 11 · 5 min Members
- Grounds that turn on causeGrounds that turn on causePayment and Defined Cost · Module 10 · 6 min Members
- Grounds that turn on the kind of costGrounds that turn on the kind of costPayment and Defined Cost · Module 10 · 6 min Members
- Sorting one applicationSorting one applicationPayment and Defined Cost · Module 4 · 6 min Members
Where you meet it
- Module 3: How Option C pays youPractitioner Course
- Module 5: Early warningsPractitioner Course
- Module 11: Defined Cost, the Schedule of Cost Components and Disallowed CostPractitioner Course
- Module 0: Key terms and the money mapPayment and Defined Cost · Free
- Module 1: How the ECC paysPayment and Defined Cost · Free
- Module 4: Defined Cost, the Fee and the Schedule of Cost ComponentsPayment and Defined Cost
- Module 5: PeoplePayment and Defined Cost
- Module 10: Disallowed Cost, ground by groundPayment and Defined Cost
- Module 11: Records, audits and clawbackPayment and Defined Cost
- Module 9: Assessing and proving compensation eventsCase Law
- Module 4: Early warning and advance warningNEC4 vs FIDIC 2017