NEC4 · ECC Option C 11.2(31)
Price for Work Done to Date
The basis of each payment. Under Option C it is the Fee plus the Defined Cost the Project Manager expects to be paid out before the next assessment.
“the total Defined Cost which the Project Manager forecasts will have been paid” (11.2(31))
On the Aldermere project
At the 4 May 2026 assessment, Defined Cost of GBP 1,900,000 plus the Fee of GBP 209,000 gave GBP 2,109,000.
Also written as
- PWDD
Lessons that teach this
- The target and the paymentThe target and the paymentPractitioner Course · Module 3 · 5 min Members
- The Contractor's shareThe Contractor's sharePractitioner Course · Module 3 · 6 min Members
- Building the amount dueBuilding the amount duePractitioner Course · Module 10 · 5 min Members
- The dates part one fixesThe dates part one fixesPractitioner Course · Module 2 · 6 min Members
- Key Dates, weather and the OptionsKey Dates, weather and the OptionsPractitioner Course · Module 2 · 6 min Members
- One assessment monthOne assessment monthPractitioner Course · Module 3 · 6 min Members
- The Contractor's shareThe Contractor's sharePractitioner Course · Module 12 · 5 min Members
- The words that move moneyPayment and Defined Cost · Module 0 · 5 min Free
Where you meet it
- Module 2: The Contract Data, before you signPractitioner Course
- Module 3: How Option C pays youPractitioner Course
- Module 10: PaymentPractitioner Course
- Module 12: Target contracts under Options C and DPractitioner Course
- Module 0: Key terms and the money mapPayment and Defined Cost · Free
- Module 1: How the ECC paysPayment and Defined Cost · Free
- Module 9: Inflation and the target under Option X1Payment and Defined Cost
- Module 12: The Contractor's share and the final accountPayment and Defined Cost
- Module 3: Getting paidNEC4 vs FIDIC 2017