NEC4 · ECC 11.2(3)
Completion Date
The date the Contractor must reach Completion by. It starts as the date written in the Contract Data and moves only under the contract, such as through compensation events.
“the completion date unless later changed in accordance with the contract” (11.2(3))
On the Aldermere project
The Completion Date of 30 April 2027 became 7 May 2027 when CE007 was implemented on 5 May 2026.
Also written as
- completion date
Lessons that teach this
- The freeze and compensation eventsThe freeze and compensation eventsPayment and Defined Cost · Module 9 · 6 min Members
- What adds timeWhat adds timeNEC4 vs FIDIC 2017 · Module 8 · 5 min Members
- Measuring delay and speeding upMeasuring delay and speeding upNEC4 vs FIDIC 2017 · Module 8 · 5 min Members
- Delay damagesDelay damagesNEC4 vs FIDIC 2017 · Module 8 · 5 min Members
- Getting delay damages paidGetting delay damages paidNEC4 vs FIDIC 2017 · Module 8 · 5 min Members
- Reading and changing the wordsPractitioner Course · Module 1 · 5 min Free
- Two parts and who fills them inTwo parts and who fills them inPractitioner Course · Module 2 · 5 min Members
- Key Dates, weather and the OptionsKey Dates, weather and the OptionsPractitioner Course · Module 2 · 6 min Members
Where you meet it
- Module 9: Inflation and the target under Option X1Payment and Defined Cost
- Module 8: Extending time and delay damagesNEC4 vs FIDIC 2017