Variation
A change to the Works that the Engineer instructs under Clause 13, directly or after a Request for Proposal. It is valued under Clause 12.
“any change to the Works, which is instructed as a variation” (FIDIC 1.1.86)
On the Aldermere project
Dana's 1 June 2026 instruction for a flatter embankment slope is Variation 1 under Sub-Clause 13.3.1.
Also written as
- Variations
- Variation by Instruction
Lessons that teach this
- Who can change the workWho can change the workNEC4 vs FIDIC 2017 · Module 6 · 5 min Members
- From instruction to decisionFrom instruction to decisionNEC4 vs FIDIC 2017 · Module 6 · 5 min Members
- Pricing first and your own ideasPricing first and your own ideasNEC4 vs FIDIC 2017 · Module 6 · 5 min Members
- How the two contracts are builtNEC4 vs FIDIC 2017 · Module 1 · 6 min Free
- When documents conflictNEC4 vs FIDIC 2017 · Module 1 · 7 min Free
- When the reply is silenceWhen the reply is silenceNEC4 vs FIDIC 2017 · Module 2 · 5 min Members
- What adds timeWhat adds timeNEC4 vs FIDIC 2017 · Module 8 · 5 min Members
- Defects and the closing certificateDefects and the closing certificateNEC4 vs FIDIC 2017 · Module 12 · 5 min Members
Where you meet it
- Module 6: Changing the workNEC4 vs FIDIC 2017