NEC4 · ECC 11.2(10)
Fee
Defined Cost multiplied by the fee percentage. It covers every cost that is not Defined Cost, such as head office overheads, plus profit.
“the amount calculated by applying the fee percentage to the amount of Defined Cost” (11.2(10))
On the Aldermere project
In CE007, Defined Cost of GBP 73,153.15 attracts a Fee at 11% of GBP 8,046.85.
Also written as
- the Fee
Lessons that teach this
- What the Fee carriesWhat the Fee carriesPayment and Defined Cost · Module 4 · 6 min Members
- Defined Cost and the FeeDefined Cost and the FeePractitioner Course · Module 11 · 5 min Members
- Defined Cost and the FeeDefined Cost and the FeePractitioner Course · Module 3 · 5 min Members
- Building the fee and the ratesBuilding the fee and the ratesContract Preparation · Module 10 · 6 min Members
- Part two: the Fee, the Working Areas and the ratesPart two: the Fee, the Working Areas and the ratesPractitioner Course · Module 2 · 6 min Members
- Testing the fee and the ratesTesting the fee and the ratesContract Preparation · Module 9 · 5 min Members
- The price tests in clause 52.1The price tests in clause 52.1Payment and Defined Cost · Module 4 · 6 min Members
- Sorting one applicationSorting one applicationPayment and Defined Cost · Module 4 · 6 min Members
Where you meet it
- Module 3: How Option C pays youPractitioner Course
- Module 11: Defined Cost, the Schedule of Cost Components and Disallowed CostPractitioner Course
- Module 0: Key terms and the money mapPayment and Defined Cost · Free
- Module 1: How the ECC paysPayment and Defined Cost · Free
- Module 4: Defined Cost, the Fee and the Schedule of Cost ComponentsPayment and Defined Cost
- Module 7: Valuing changeNEC4 vs FIDIC 2017
- Module 3: How the main Options pay the ContractorContract Preparation
- Module 10: The tenderer's viewContract Preparation