NEC4 · ECC W1.3(1)

notice of adjudication

The notice that starts an adjudication. Under W1 it comes within two weeks after the Senior Representatives list the issues, and the referral within a week after that.

On the Aldermere project

For CE014, the notice of adjudication went on 1 September 2026 and the referral on 7 September.