Claim
One Party's request to the other for something it says the contract entitles it to, such as more time or money. Either Party can claim.
“a request or assertion by one Party to the other Party for an entitlement” (FIDIC 1.1.6)
On the Aldermere project
Claim 1 is Merrow Vale's Red Book Claim for the buried concrete, settled at EOT 7 days and GBP 76,500.
Also written as
- Claims
Lessons that teach this
- Two tests for the groundTwo tests for the groundNEC4 vs FIDIC 2017 · Module 5 · 5 min Members
- Notices and time barsNotices and time barsNEC4 vs FIDIC 2017 · Module 5 · 5 min Members
- From notice to decisionFrom notice to decisionNEC4 vs FIDIC 2017 · Module 5 · 5 min Members
- When nobody decidesWhen nobody decidesNEC4 vs FIDIC 2017 · Module 5 · 5 min Members
- How the two contracts are builtNEC4 vs FIDIC 2017 · Module 1 · 6 min Free
- Who does whatNEC4 vs FIDIC 2017 · Module 1 · 7 min Free
- Communications that countNEC4 vs FIDIC 2017 · Module 1 · 7 min Free
- How work startsHow work startsNEC4 vs FIDIC 2017 · Module 2 · 5 min Members
Where you meet it
- Module 1: Two contracts, one schemeNEC4 vs FIDIC 2017 · Free
- Module 5: Compensation events and ClaimsNEC4 vs FIDIC 2017