NEC4 · ECC 11.2(8)
Early Warning Register
The Project Manager's list of risk matters, from the Contract Data or early warnings, and how each will be avoided or reduced. It is revised after each early warning meeting.
“notified by the Project Manager or the Contractor as early warning matters” (11.2(8))
On the Aldermere project
Dana issued the first Early Warning Register on 16 January 2026 and a revised one on 10 March.
Lessons that teach this
- What to warn of, and howWhat to warn of, and howPractitioner Course · Module 5 · 6 min Members
- The register and the meetingsThe register and the meetingsPractitioner Course · Module 5 · 6 min Members
- Giving an early warningGiving an early warningCase Law · Module 7 · 6 min Members
- Registers and meetingsRegisters and meetingsNEC4 vs FIDIC 2017 · Module 4 · 6 min Members
- The price of not warningThe price of not warningNEC4 vs FIDIC 2017 · Module 4 · 6 min Members
- The NEC4 family and the short formsContract Preparation · Module 1 · 5 min Free
- Two parts and who fills them inTwo parts and who fills them inPractitioner Course · Module 2 · 5 min Members
- What mutual trust asksWhat mutual trust asksCase Law · Module 2 · 6 min Members
Where you meet it
- Module 5: Early warningsPractitioner Course
- Module 7: Early warning, prevention events and accelerationCase Law
- Module 4: Early warning and advance warningNEC4 vs FIDIC 2017