FIDIC 2017 · FIDIC 1.1.73
Section
A portion of the Works that the Contract Data sets up as a Section, with its own Time for Completion. The ECC equivalent comes from Option X5.
“a part of the Works specified in the Contract Data as a Section” (FIDIC 1.1.73)
On the Aldermere project
The Aldermere Red Book contract has no Sections.
Also written as
- Sections
Lessons that teach this
- Who warns, and of whatWho warns, and of whatNEC4 vs FIDIC 2017 · Module 4 · 5 min Members
Where you meet it
- Module 4: Early warning and advance warningNEC4 vs FIDIC 2017