FIDIC 2017 · FIDIC 20.2.4
fully detailed Claim
The full Claim submission, with the event, its legal basis, the records and the amount or EOT sought. It is due within 84 days of awareness.
“a statement of the contractual and/or other legal basis of the Claim” (FIDIC 20.2.4)
On the Aldermere project
Merrow Vale's fully detailed Claim for the buried concrete was received on 29 April 2026, inside the 84 days.