Statement at completion

The Contractor's first Statement after taking over, due within 84 days. It values all work done by the Date of Completion and lists any further sums claimed.

On the Aldermere project

The Statement at completion was due by 18 August 2027. Merrow Vale sent it on 10 August 2027.