Waleed Tariq Academy

NEC4 · ECC 50.3

amount due

The running total owed at an assessment date: the Price for Work Done to Date plus other sums, less deductions. Each payment is the change since the last.

On the Aldermere project

The amount due on 4 May 2026 was GBP 2,057,730. With GBP 1,500,000 due at 6 April, the payment was GBP 557,730.

Also written as