NEC4 · ECC Option X16

Option X16

Retention, which cannot be used with Option F. A percentage of the Price for Work Done to Date above the retention free amount is held back, half released after Completion.

On the Aldermere project

Aldermere uses X16 at 3% above a retention free amount of GBP 400,000.