NEC4 · ECC Option C 54.1
total of the Prices
The sum of all the Prices. Under Option C it is the target and moves as compensation events are implemented. Option D has its own defined Total of the Prices.
On the Aldermere project
The total of the Prices moved from GBP 8,400,000 at the Contract Date to GBP 8,912,000 at the end.
Also written as
- tendered total of the Prices
Lessons that teach this
- What moves the target and what forecasts doWhat moves the target and what forecasts doPayment and Defined Cost · Module 12 · 5 min Members
- The target and what moves itThe target and what moves itPractitioner Course · Module 12 · 5 min Members
- The Contractor's shareThe Contractor's sharePractitioner Course · Module 12 · 5 min Members
- Where the adjustment goesWhere the adjustment goesPayment and Defined Cost · Module 9 · 6 min Members
- Work out the Contractor's shareWork out the Contractor's sharePayment and Defined Cost · Module 12 · 6 min Members
- The Contractor's shareThe Contractor's sharePractitioner Course · Module 3 · 6 min Members
- What to warn of, and howWhat to warn of, and howPractitioner Course · Module 5 · 6 min Members
- The money when a contract endsThe money when a contract endsPractitioner Course · Module 15 · 6 min Members
Where you meet it
- Module 12: Target contracts under Options C and DPractitioner Course
- Module 9: Inflation and the target under Option X1Payment and Defined Cost
- Module 12: The Contractor's share and the final accountPayment and Defined Cost