NEC4 · ECC 50.2

application for payment

The Contractor's statement, sent before an assessment date, of the amount it considers due. Without one, the amount due cannot rise above the previous amount due.

On the Aldermere project

Merrow Vale's 30 June 2026 application was late, so the 29 June amount due was capped and that payment was nil.

Also written as

  • applications for payment