NEC4 · ECC 53.3
conclusive evidence
The status the final assessment gains unless a Party starts the dispute steps in time. After that, neither Party can reopen the final amount due.
On the Aldermere project
The 16 June 2028 final assessment becomes conclusive unless a dispute reaches the Senior Representatives by 14 July 2028.
Also written as
- conclusive
Lessons that teach this
- When the assessment becomes conclusiveWhen the assessment becomes conclusivePractitioner Course · Module 14 · 6 min Members
- Test each audit finding against its evidenceTest each audit finding against its evidencePayment and Defined Cost · Module 11 · 6 min Members
- The final assessment and what follows a terminationThe final assessment and what follows a terminationPayment and Defined Cost · Module 12 · 6 min Members
- Build the final amount due and the final paymentBuild the final amount due and the final paymentPayment and Defined Cost · Module 12 · 6 min Members
- Who must prove it was wrongWho must prove it was wrongCase Law · Module 10 · 6 min Members
Where you meet it
- Module 14: The final assessment and closing outPractitioner Course
- Module 11: Records, audits and clawbackPayment and Defined Cost
- Module 12: The Contractor's share and the final accountPayment and Defined Cost
- Module 10: Payment, Defined Cost and the shareCase Law